Behaviour of an underground metro station for different constitutive models - A study on the influence of Mohr-Coulomb and other advanced constitutive models using PLAXIS 2D for the proposed Chennai Metro Rail Phase 2 project
IOP Conference Series: Earth and Environmental Science Pub Date : 2021-04-23 , DOI: 10.1088/1755-1315/703/1/012047
N Kumar Pitchumani 1 , Ganesh Deepak Kanchuboyina 2 , R K Anjana 3 , Sai Krishna Bugga 4
Affiliation  

The Phase 2 of the proposed Chennai Metro Rail Project contains underground stations of depths below ground varying from 20m for a 2 level station to 32m for a 4 level station. Diaphragm walls have been chosen for the purpose of earth retention during construction stage and also to be a part of the permanent structure. The centre part of the stations is constructed using top-down methodology and the ends of the station which are used for the purpose of TBM launching and retrieval activities are constructed using either bottom-up or top-down methodologies. The behaviour of the part of the station constructed using top down sequence will be different from the part constructed using bottom up sequence. The current study focusses on the comparison of the influence of the various constitutive models available in the FEM software package PLAXIS 2D such as the basic Mohr-Coulomb model and advanced models such as Hardening soil model and Hardening soil small strain stiffness (HSS) models on the bending moments, shear forces of the diaphragm walls, ground deformations, strut forces etc. This comparative study has been performed on both the top-down and bottom-up sequences and for the different ground conditions along the proposed second phase metro rail alignment in Chennai region of India.



中文翻译:

不同本构模型下地铁站的行为 - 使用 PLAXIS 2D 研究 Mohr-Coulomb 和其他高级本构模型对拟建的钦奈地铁二期项目的影响

拟建的钦奈地铁项目二期包含地下深度从 20m 的 2 层站到 32m 的 4 层站的地下站。选择隔膜墙是为了在施工阶段保持土,同时也是永久性结构的一部分。站的中心部分采用自上而下的方法建造,用于 TBM 发射和回收活动的站的末端采用自下而上或自上而下的方法建造。使用自顶向下序列构建的站点部分的行为将不同于使用自底向上序列构建的部分。