Volume 141, September 2022, 104450
Automation in Construction

Dynamic control for construction project scheduling on-the-run

https://doi.org/10.1016/j.autcon.2022.104450Get rights and content
Under a Creative Commons license
open access

Highlights

  • Introducing the Mitigation Controller for the most effective and efficient control of construction projects on-the-run.

  • Developing and incorporating contractual performance schemes (penalty/reward) for timely construction project completion.

  • Introducing a rigorous approach to account for stochastic correlations between the durations of the construction activities.

  • Demonstrating its application for a real-life Dutch infrastructure project.

Abstract

Construction project management requires dynamic mitigation control to ensure a project's timely completion. Current mitigation approaches are usually performed by an iterative Monte Carlo (MC) analysis which does not reflect (1) the project manager's goal-oriented behavior, (2) contractual project completion performance schemes, and (3) stochastic dependence between construction activities. Therefore, the development statement within this paper is to design a method and implementation tool that properly dissolves all of the aforementioned shortcomings ensuring the project's completion date by finding the most effective and efficient mitigation strategy. For this purpose, the Mitigation Controller (MitC) has been developed using an integrative approach of nonlinear stochastic optimization techniques and probabilistic Monte Carlo analysis. MitC's applicability is demonstrated using a recent Dutch large infrastructure construction project showing its added value for dynamic control on-the-run. It is shown that the MitC is a state-of-the-art decision support tool that a-priori automates and optimizes the search for the best set of mitigation strategies on-the-run rather than a-posteriori evaluating the potentially sub-optimal and over-designed mitigation strategies (as commonly done with modern software such as Primavera P6).

Keywords

Stochastic construction scheduling
Mitigation control on-the-run
Probabilistic time-cost optimization
Penalty and reward scheme
Construction activity correlation