Introduction

Offshore oil and gas exploration began on the Grand Banks off the eastern Canadian province of Newfoundland in 1966, with the first major discovery, Hibernia, occurring in 1979. Other major discoveries followed with Hebron in 1981 and the Terra Nova and White Rose fields in 1984. Remote with limited infrastructure and exposed to the harsh and unforgivingFootnote 1 environment of the Northwest Atlantic Ocean, project economics are challenging, and developments in the region have required extensive engineering and long periods to sanction. Hibernia and Terra Nova came on-stream 18 years after discovery; White Rose took 21 years; Hebron took 37 years.

The areas where commercial oil deposits have been discovered are located on the continental shelf about 300–350 km southeast of St. John’s, Newfoundland, in water depths between 80 and 125 m (Fig. 1). The Grand Banks contains several Mesozoic basins that were formed by rifting and seafloor spreading associated with the fragmentation of Pangea in the Late Triassic that lead to the formation of the Atlantic Ocean (Fig. 2). Rocks of the Upper Jurassic sediment are the principle source for much of the hydrocarbons in the North Atlantic areas, including the Jeanne d’Arc sedimentary basin, the only currently producing region on the Grand Banks.Footnote 2 The meta-ocean conditions in the region are like the North Sea with large wavesFootnote 3 and severe storm conditions (Carrick et al. 2005), but sea ice and icebergs represent a severe hazard not present in the North Sea. Without active management (Fig. 3), about one iceberg impact per structure is expected to occur every 10 years! Pack ice,Footnote 4 icebergs, and bergy bits are prevalent in the late winter/spring, and fog is a frequent phenomenon in the summer months.

Figure 1
figure 1

Source: GoogleEarth

Continental shelf of Newfoundland and Nova Scotia, east coast of Canada.

Figure 2
figure 2

Source: White Rose DA volume 2 (development plan)

Distribution of Mesozoic basins offshore Newfoundland.

Figure 3
figure 3

Source: C-NLOPB, C-CORE

Conventional single-line method for iceberg towing.

From 1966 to 2019, operators have spent a total of $84 billion Canadian dollars in exploration, development, and production activities offshore Newfoundland and Labrador, approximately $15 billion in exploration, $36 billion in development, and $33 billion in production (Fig. 4). Throughout this paper, all expenditure data are inflation-adjusted and reported in 2019 Canadian dollars using inflation rates prepared by the Bank of Canada, unless otherwise noted. Spending adjustments for offshore exploration, development, and production activities may vary significantly from a consumer goods perspective, but for comparative purposes and consistent interpretation, inflation adjustment is necessary.

Figure 4
figure 4

Source: Data from C-NLOPB

Exploration, development, and production expenditures offshore Newfoundland adjusted to 2019 Canadian dollars, 1966-2019.

To date, two development concepts have been employed in the region, concrete gravity-base structures (GBS) and floating production storage and offloading (FPSO) vessels. Both strategies are designed to receive oil and gas from platform wells and/or subsea systems, process well fluids using equipment on the structure, storing oil until transferred by shuttle tankers to shore. There are no export pipelines in the region for either oil or gas, and all surplus gas is compressed and reinjected back into reservoirs. Gas reinjection helps maintain reservoir pressure and facilitates crude recovery, with the gas stored for possible production in the future. GBSs are installed to drill wells from the platform but can also employ subsea wells out of reachFootnote 5 of the platform rig, while FPSO developments require a mobile offshore drilling unit (MODU) in well construction and service (i.e., all FPSO wells are subsea wells).

Concrete platforms for oil and gas development were built in the Gulf of Mexico in the 1950s for shallow water fields and reached their maximum depth at the Troll A structure in 303 m in the North Sea in 1996 (Mikkelsen et al. 2005). Only 30 GBSs have been installed worldwide, most in the North Sea, two offshore Newfoundland, and one in southeast Asia. The inherent strength and stability of GBSs can support large topsides weight with drilling and production and can be designed to withstand the impactFootnote 6 of a large iceberg. Platform rigs drill dry wells, also called dry tree wells since the tree is above the waterline, which reduce drilling cost and improve well maintenance, lower operating costs, and have a greater resource recovery compared to subsea wells. GBSs have several advantages for iceberg-affected regions not subject to significant sheet ice, but they require a large reserves base to support the large capital expenditures and require extensive project management and a long construction cycle.

FPSOs also have many advantages in offshore oil and gas development. Like GBSs, they arrive at site with topsides already in place, and much of the installation can be completed onshore/inshore. They are built based on conventional shipbuilding technology and have a large workspace with heavy payload capacity, and they offer easy installation and decommissioning. About 200 FPSOs are deployed worldwide and under construction circa 2020 ranging from the Barents Sea offshore Norway to Australia (Offshore Magazine 2019). FPSOs provide a flexible development strategy with advantages in reduced capital investment, varied ownership and operatorship options, and accelerated schedule. FPSOs are not designed for iceberg impacts, however, except small bergy bits, and pack ice conditions must be minor. Drilling operations cannot be performed on deck due to the motion characteristics of the vessel, so all FPSO wells are subsea. If an iceberg presents a risk of collision, the FPSO must disconnect from its turret and risers and exit the area to avoid contact.

In the early days of Grand Banks exploration, ice avoidance was the prevailing philosophy during drilling. Close encounters with icebergs could force a MODU to stop drilling and evacuate or prepare for impact, which can significantly increase the cost and risk of operations, and in the case of FPSOs, to disconnect and leave the area in the event of unmanageable ice. Today, there is a joint regional ice management plan that enables coordinated responses for all the operators on the Grand Banks. The plan provides for coordination of ice and iceberg detection, monitoring and trajectory projection, and coordinated management of response actions to icebergs transiting the areas that present risk to drilling and production. The iceberg management system includes definition of alert and exclusion zones, and coverage surveillance using satellite imagery and aerial flights.

The purpose of this review is to evaluate the exploration, development, and production cost offshore Newfoundland using publicly available data. In most producing areas of the world, detailed field data are unavailable and require expensive commercial subscription services to access, but in a few countries (e.g., Canada, Norway, UK, USA), reliable data are available from government agencies. Newfoundland is one of the most transparent regions, especially regarding spending levels and well reports, and in this paper we review the cost components leading to production. For development drilling and production, data provides useful results; for exploration drilling and production cost, more inferences are needed, and results are less robust. This is the first detailed analysis of exploration, development, and production cost offshore Newfoundland.

The outline of the rest of this paper is as follows. The license areas offshore Newfoundland and Labrador introduce the setting and are followed by a summary of exploration activity, producing fields, development activity, production, and reserves. Exploration cost per well and depth drilled is estimated, along with related summary statistics, and development drilling trends and average cost for MODU wells are examined. The strategies and trade-offs for iceberg-prone developments are highlighted, as well as employment data associated with each project. With only four projects in the region, each is examined individually. The paper concludes with an evaluation of unit development and production costs. In three appendices, information on iceberg management, drilling time and cost curves, and reservoir management requirements are described. A primer on icebergs and the ice management plans employed by operators is summarized since it is a unique and interesting feature of development in the region. Time vs. depth and time vs. cost curves are used in development well cost analysis and are briefly reviewed for readers encountering them for the first time.

License Terms

The Canada–Newfoundland and Labrador Offshore Petroleum Board (C-NLOPB) is the regulatory agency overseeing oil and gas activities offshore Newfoundland and Labrador within Canada’s exclusive economic zone (EEZ) and issues land rights in the form of Exploration Licenses (ELs), Significant Discovery Licenses (SDLs), and Production Licenses (PLs) (Fig. 5).

Figure 5
figure 5

Source: C-NLOPB

Newfoundland and Labrador offshore license information, January 2020.

Under international law, coastal states have sovereignty and jurisdiction over their territorial sea, defined from the coastline to a 12 nautical mile (nm)Footnote 7 limit, and these rights cover the resources of the surface, water column, seabed, and subsoil, and extend vertically to the airspace. In other words, the 12-nm coastal zone is considered, for all practical purposes, identical to a nation’s land. Unlike the territorial sea, which derived from conventions going back hundreds of years, the exclusive economic zone (EEZ) was a relatively recent creation of the UN Law of the Sea Convention (UNCLOS) in 1982 and provides a coastal state a maritime boundary extending 200 nm (370 km, 230 mi) from their coastline where they are granted exclusive economic rights to regulate fisheries, mineral development, and environmental protection. The EEZ is not sovereign water, but exclusive economic rights can be quite valuable.

Canada’s EEZ covers the majority of the continental shelfFootnote 8 offshore Newfoundland and Labrador, except for the “nose” on the eastern extremity, near the Flemish Cap, which is beyond the EEZ limit, and the “tadpole” surrounding the French territories of St. Pierre and Miquelon that juts south of the island.

According to UNCLOS, a country may also claim an extended continental shelf beyond the 200 nm (370 km, 230 mi) granted to all coastal nations by their EEZ. States present geological evidence to a UN commission, which judges the scientific validity of assertions. Countries with rightful but overlapping claims are expected to come to a settlement. Article 76 of UNCLOS outlines limits of the continental shelf that a country can claim, either 350 nm (648 km) from the baseline, or 100 nm (185 km) from the 2500-m isobath. For submarine ridges, only the 350 nm (675 km) limit is applicable. Coastal states seek to claim the largest continental shelf that is (legal) within the rules established by UNCLOS. Canada has submitted its application to the UN for an extended continental shelf claimFootnote 9 offshore Newfoundland and Labrador.

ELs may extend to a maximum nine-year term if a well is spudded within the first period (either 5 or 6 years) from the date of issuance. SDLs acknowledge an owner’s right to hold interests indefinitely where the area has potential for sustained production of petroleum. PLs permit an owner to produce petroleum from an interest, consistent with approvals and authorization from the C-NLOPB.

Exploration Drilling

Well Type

Exploration and development wells are used to find commercial accumulations of hydrocarbons and develop them. Exploration wells are drilled outside known reservoirs, and therefore, exploratory drilling almost alwaysFootnote 10 takes place from a MODU such as a jack-up, semisubmersible or drillship. Development drilling is different from exploration drilling, since the objective is to produce, while in exploration the objective is to find hydrocarbons, and in appraisal, to delineate the reservoir and gather the necessary data for planning the development. Delineation wells are used to determine the areal and vertical extent of reservoirs and have many similarities to exploration wells.

In exploration drilling, pressure regions are unknown which result in conservative mud weight practices and casing design and slower rate of penetrations. This typically results in slow, expensive wells. Exploration wells are also almost always drilled vertically straight down to target unless bypass and sidetracks are required. If exploration is not successful, sidetracks may be drilled prior to abandonment to better understand the formation geology, which adds to the cost of the well. Onshore, most successful exploration wells transform into producer (development) wells since land and infrastructure requirements are not constraining, while offshore, this is much less common. Delineation drilling typically includes coring, fluid sampling, drill stem tests, etc., which also contributes to high drilling cost.

Exploration Expenditures

From 1966 to 2018, 173 exploration wells and 59 delineation wells were drilled offshore Newfoundland and Labrador, and operators spent $14.6 billion on exploration activities during the period (Fig. 6). Most drilling occurred east of Newfoundland in the Jeanne d’Arc sedimentary basin and surrounding area (168 exploration wells, 55 delineation wells), with the remaining wells drilled west and south of Newfoundland and offshore Labrador. Exploration expenditures include seismic surveys, well site surveys, well testing, and drilling operations. Well cost includes new wells spudded and drilled, wells reentered and drilled, and well abandonment. Exploration and delineation wells are grouped together in evaluation since both are drilled using MODUs with relatively simple trajectories and similar cost characteristics.Footnote 11

Figure 6
figure 6

Source: Data from C-NLOPB

Exploration expenditures and number of exploration and delineation wells drilled offshore Grand Banks, Newfoundland.

From 1966 to 1988, about $8.2 billion was spent in exploration on the Grand Banks and all the major discoveries were made during this time. Over the next decade, many fewer exploratory wells were drilled as operators focused on developing their discoveries. Only about $500 million was spent from 1989 to 1998 on exploration, and for several years during this period, no exploratory drilling occurred. Beginning in 1999, operators began to explore further afield, and another wave of exploratory activity occurred in the most recent decade. From 1999 to 2008, about $1.6 billion was spent on exploration, and from 2009 to 2018, $4.3 billion was spent.

Exploration Well Cost

From 1966 to 2018, 555,084 m of borehole was drilled in exploration wells, 193,161 m in delineation drilling, and 28,241 m in reentered exploration/delineation wells (Fig. 7). Measured depth is a primary cost factor which along with the diameter of the borehole determines the volume of rock that must be broken up and removed. The market rates of MODUs and unplanned events (e.g., weather) are also significant factors in well construction cost.

Figure 7
figure 7

Source: Data from C-NLOPB

Borehole drilled in exploration, delineation, and reentry exploration and delineation wells offshore Grand Banks, Newfoundland.

From 1966 to 2018, total aggregate cost per meter drilled is estimated to be $14,235/m and average aggregate well cost was $67.7 million/well. The average annual well cost and average meter drilled were $90.9 million/well and $26,494/m (Fig. 8). Aggregate (composite) annual cost is the sum of all well cost divided by the number of wells and total meters drilled. Average annual statistics are computed over the period year-by-year. Composite averages are always smaller than average cost due to the manner of computation.

Figure 8
figure 8

Source: Data from C-NLOPB

Average inflation-adjusted exploration and delineation well cost and cost per meter drilled offshore Grand Banks, Newfoundland.

From 1998 to 2018, 42 exploration wells and 31 delineation wells were drilled at a total cost of $5993 million, or $82 million per well. The average measured depth drilled during this period was 7253 m per well. Reentered wells are not counted as new wells, but new borehole is allocated in the year incurred. Some wells are reentered in later years one or more times, but for exploration and delineation drilling, relatively few wells are later reentered (28,241 m total, or about 4% borehole drilled). Composite cost per meter drilled during this period was $22,690/m.

Individual well cost is not reported, only total exploration spending per year, which covers all wells spud and the cost of reentries performed during the year along with ancillary activities, and so the statistics computed are an approximation to actual well cost. Exploration/delineation well campaigns may overlap consecutive years, and companies may allocate costs between years, which will further distort the statistics.

Operators occasionally report exploration well expenditures in their development applications, and this is useful information for comparison. For example, in the Hebron project, ExxonMobil reported exploration cost for seven wells drilled from 1980 to 1999. The average cost reported was $53.3 million/well and $13,278 per meter drilled and ranged between $24 and $111 million, with median cost $41.3 million (all unadjusted). At White Rose, exploration well cost averaged $30 and $57 million per well over two delineation campaigns in 1984–1986 and 1989–1992, respectively (all unadjusted).

In terms of wells drilled, exploration and delineation activity has been low over the past two decades, typically less than three wells per year, although activity levels are occasionally higher. The maximum average well cost reached $220 million and $80,000 per meter.

Fields

The Hibernia field was discovered in 1979 and began producing in 1997 from a GBS in 80 m water depth operated by Hibernia Management and Development Company Ltd. (Fig. 9). Hibernia oil is a light sweet low-acid crude with a density of 32–34°API, a sulfur content of 0.4–0.6 wt%, and a total acid number of 0.09 mg/g. Recoverable reserves at Hibernia are estimated at 1644 MMbbl (260 million m3).Footnote 12

Figure 9
figure 9

Source: Hibernia Management and Development Company, Suncor Energy, Husky Oil, ExxonMobil Canada

Clockwise from top left: Hibernia gravity-base structure, Terra Nova FPSO, Sea Rose FPSO, Hebron gravity-base structure.

Discovered in 1984 about 23 nm (43 km) southeast of Hibernia, the Terra Nova field consists of one reservoir, the Jeanne d’Arc, which began producing in 2002. A double-hull ice-strengthened disconnectable FPSO in 100 m water depth operated by Suncor Energy Inc. is used in development (Fig. 9). Terra Nova oil is a light (34°API), sweet (0.52 wt% sulfur), low-acid (0.03 mg/g) crude. Recoverable reserves are estimated at 506 MMbbl (80 million m3).

The White Rose field was discovered in 1984 in 120 m water depth about 30 nm (56 km) northeast of Hibernia. White Rose has one principal reservoir, the Ben Nevis–Avalon, which began producing in 2005 from a FPSO operated by Husky Oil (Fig. 9). Recoverable reserves are estimated at 404 MMbbl (80 million m3). In 2010, the 75 MMbbl (12 million m3) North Amethyst subsea tieback began production through the White Rose facilities, and the West White Rose extension planned to use a gravity-base wellhead platform for drilling but was suspended c.2020 due to the Covid-19 pandemic, China’s gift to the world, and future operation is under review.

The Hebron field was discovered in 1980 about 5 nm (9 km) north of Terra Nova and 17 nm (31 km) southeast of Hibernia. First production was in 2017 from a GBS in 92 m water depth operated by ExxonMobil Canada Properties (Fig. 9). The field produces a heavy sour acidic crude (20°API, 0.92 wt% sulfur, 1.2 mg/g). Recoverable reserves are estimated at 707 MMbbl (112 million m3).

Development Drilling

Drilling and Completion

Development well construction includes two distinct operations—drilling the well to total depth and completing the well through installation of the tree. Development wells include producer and injection (gas, water) wells and disposal wells, and all successful development wells require completion. Well completion represents the installation of packers, screens, and other hardware coupled with perforations and stimulation. The goal of drilling is to drill the well to target depth at minimum cost in a safe and environmentally sound manner in accord with all applicable laws and regulations. The goal of completion is to achieve high-rate long-life completions to maximize production rates and resource recovery.

Drilling cost depends on location (onshore, offshore), purpose of the well (exploration, delineation, development), trajectory (vertical, directional, horizontal), borehole size and complexity (two-dimensional, three-dimensional, extended reach), type (original, sidetrack), measured depth, drilling plan (number of casings, mud weight, maximum angle, etc.), drilling program (sequence, batch, number of wells drilled), formations encountered, rig type (MODU, platform), market conditions, problems, weather, crew experience, planning, and various other factors.

Completions are the interface between the well and the reservoir, and completion cost is impacted by type (single, multiple), complexity (gravel pack, frac pack, smart), stimulation requirements, reservoir management and downhole equipment (pressure and temperature gauges, chemical injection, gas lift), time of development, and other factors. Smart completions refer to downhole equipment and sliding sleeves that allow controlling production from multiple zones.

Development Activity

Through mid-2020, 261 development wells have been drilled offshore Newfoundland: 133 at Hibernia, 56 at Terra Nova, 52 at White Rose/North Amethyst, and 22 at Hebron (Fig. 10). The first development well was drilled at Hibernia in 1997 after the GBS was installed—indeed, the main reason for the selection of the GBS was the advantages of dry tree wells in development—whereas at Terra Nova and White Rose/North Amethyst, all development wells are drilled from MODUsFootnote 13 with development drilling occurring before and after facility installation. More than half of development drilling at Terra Nova and White Rose/North Amethyst circa 2020 has occurred after first production (Table 1).

Figure 10
figure 10

Source: Data from C-NLOPB

Development wells drilled offshore Grand Banks, Newfoundland, 1997–2019.

Table 1 Development wells drilled offshore Newfoundland through 2019.

The total borehole drilled in development wells is about twice the total measured depth of exploration wells, 1.32 million meters vs. 777,000 m circa 2020. Measured depth is measured along the path of the wellbore. At Hibernia, 772,648 m development wellbore has been drilled through 2019, 226,644 m at Terra Nova, 172,141 m at White Rose, 68,957 m at North Amethyst, and 76,253 m at Hebron (Fig. 11). Hebron is still early in its development campaign. A strong correlation arises between development well counts and total measured depth drilled because of similar regional geology of producing formations. In Fig. 12, the regression yields a robust model fit (R2 = 0.97):

$$ {\text{Measured depth}}\;\left( {\text{m}} \right) = 4849\; \cdot \;{\text{Well count}}. $$

Since operators are producing from the same trend and relatively narrow intervals within those trends, and because development well profiles are broadly similar across the four projects, the strong fit of the regression is not surprising.

Figure 11
figure 11

Source: Data from C-NLOPB

Borehole drilled in development and reentry development wells offshore Grand Banks, Newfoundland, 1997–2019.

Figure 12
figure 12

Source: Data from C-NLOPB

Relationship between amount of borehole drilled and number of development wells (top) and correlation (bottom) offshore Newfoundland, 1997–2019.

It normally takes 2–3 months on average to drill and complete one well from a platform rig, and so at Hibernia, the number of development wells drilled during its early years was limited to about 12 wells per year from its two active drill rigs. Hebron has one rig, and well counts are limited to about 6 wells per year. For wells drilled from a MODU, drilling and completion time is a bit longer, but wells are also usually simpler so annual well counts per rig are about the same.

Development Well Cost

End of Well reportsFootnote 14 are required by the Newfoundland Offshore Petroleum Drilling and Production Regulations and is a regulatory submission to C-NLOPB. End of Well reports serve as a record of operations performed during the drilling and completion of wells.

Two of Newfoundland’s offshore projects (Terra Nova and White Rose/North Amethyst) provide cost data in End of Well reports. Hibernia and Hebron do not report cost data, except in special cases, and so no comparisons can be made between MODU wells and platform wells. Also, not surprisingly, data from recent wells are somewhat more comprehensive and complete than early End of Well reports, which may not include cost vs. depth curves or completion cost.

Well type and well status are primary categories in the cost evaluation. Producers and injectors have been drilled and completed while suspended wells are in an indeterminate (suspended) state, on their way to completion, or on their way to abandonment, if unsuccessful. Suspended wellsFootnote 15 are not considered in evaluation unless their status is clearly defined (e.g., suspended for completion). During drilling, wells may be abandoned if problems arise or a productive zone cannot be found. Abandoned producer and abandoned injector wells were previously completed and are included in evaluation without abandonment cost.

Of the 105 wells reported, about two-thirds are producer and injector wells, and the remaining wells are in various indeterminate states which were not evaluated. Not all producer and injector wells provide both drilling and completion cost data, so separate categories are provided for drilling, completion, and drilling and completion (D&C) well cost. Drilling cost and D&C cost are normalized in terms of measured depth. For a brief review on time–depth and cost–depth plots, see Appendix B.

A total of 35 producers and 26 injector wells from 1999 to 2019 provide drilling and completion cost data. At Terra Nova, $2.2 billion was spent from 1999; at White Rose, $2.5 billion was spent from 2003; and at North Amethyst, $1.3 billion was spent from 2009. The average D&C producer well cost was $91.1 million, and the average injector D&C cost was $68.8 million. The standard deviation of the sample data for producer wells was $42 million and $45 million for injector wells. D&C cost distribution for all producer and injector wells in the sample is shown in Fig. 13.

Figure 13
figure 13

Source: Data from C-NLOPB

Development cost distribution for production and injection wells from FPSO developments offshore Newfoundland, 1999–2019.

At Terra Nova and White Rose, producer wells cost more to construct than injector wells, while at North Amethyst injector wells cost more than producer wells, due either to small sample bias and/or more complex/problematic injector wellbores. In total, Terra Nova wells cost $69.3 million per well and $15,923/m; White Rose wells cost $79.4 million per well and $16,349/m; and North Amethyst wells cost $107.7 million per well and $23,990/m (Table 2). Cost distributions for each well class are depicted in Figure 14.

  • For Terra Nova production wells, the average D&C cost was $80.8 million per well and $18,945/m. On average, for the five wells reporting completion cost, completions represented 25% total well cost. The most expensive producer well was drilled in 2019 and cost $136 million, and the three most expensive producer wells were drilled from 2013 to 2019. For the 10 injection wells, average D&C cost was $52 million per well and $11,093/m, and the most expensive well was $153 million.

  • For White Rose production wells, the average D&C cost was $95.8 million per well and $17,623/m. For injection wells, the average D&C cost was $84.3 million per well and $15,117/m. Drilling and completion cost for White Rose producer wells was about $10 million more than injector wells, and about $2500 more per meter. Completion cost for producer and injector wells represented about 30% of the total well cost.

  • For North Amethyst production wells, the average D&C cost was $103.7 million per well and $20,533/m. For injection wells, the average D&C cost was $116.1 million per well and $31,148/m. Drilling and completion cost for North Amethyst injector wells was about $13 million more than injector wells, and about $10,600 more per meter, but small samples and/or the complexity of the wells may be partially responsible for the high cost.

Table 2 Development well cost statistics at Terra Nova, White Rose, and North Amethyst, 1999–2019.
Figure 14
figure 14

Source: Data from C-NLOPB

Drilling and completion cost distribution for producer (top) and injector (bottom) wells in FPSO developments offshore Newfoundland, 1999–2019.

Production and Reserves

Through February 2020, 1.94 billion barrels (308 million m3) of crude oil and 3.14 trillion cubic feet (88.2 billion m3) of natural gas have been produced offshore Newfoundland (Table 3; Fig. 15). Production peaked in 2007 at 134 million barrels (MMbbl) or 368,000 barrels of oil per day (bopd) [21 million m3 or 58,400 m3/d].

Table 3 Cumulative production offshore Newfoundland through March 2020.
Figure 15
figure 15

Source: Data from C-NLOPB

Oil production offshore Newfoundland, 1997–2019.

Natural gas associated with oil production is not a sales product and, after fuel use and gas lift, is compressed and reinjected for pressure maintenance and potential later extraction. Some gas is flared for safety purposes. A significant amount of water is also produced with black oil reservoirs, and 1.25 billion barrels (198 million m3) was separated and treated through February 2020 (Table 3). Oil and water production tends to correlate with one another in aquifer driveFootnote 16 reservoirs after a period (Fig. 16) and is readily observed at individual fields (Fig. 17).

Figure 16
figure 16

Source: Data from C-NLOPB

Total oil and produced water volumes offshore Newfoundland, 1997–2019.

Figure 17
figure 17

Source: Data from C-NLOPB

Oil and water production at Hibernia (top), Terra Nova (middle), and White Rose (bottom), 2006–2018.

Gas disposition and water injection totals per project through March 31, 2018, are shown in Table 4. Hebron data are not depicted because the field only came on-stream in late 2017. Note that gas flared, fuel, and injected totals 2782 Bcf (79 billion m3), and are equal to gas production, since lift gas is recirculated within the system. About 7% of gas production has been flared and another 8% used for fuel, with the remaining 85% reinjected. Gas reinjection is used to maintain reservoir pressure and displace the oil, and with the gas stored it may be recovered in the future.

Table 4 Field production statistics cumulative to March 31, 2018.

Water is injected into formations for voidance replacement in aquifer drive reservoirs, and normal practice is to inject volumes approximately equal to the oil and water volumes produced. Through March 31, 2018, 1760 MMbbl oil and 1122 MMbbl water (279 million m3 oil and 178 million m3 water) was produced, or 2882 MMbbl (457 million m3) fluids total, and 2927 MMbbl (464 million m3) water was injected. On a field basis, injection-to-production ratios range from 0.73 at White Rose to 1.06 at Hibernia. For additional background on produced water, water and gas injection requirements offshore, see Appendix C.

Petroleum reserves offshore Newfoundland are estimated at 3.34 billion barrels (530 million m3), with resources estimated at 573 MMbbl oil, 8.3 Tcf natural gas, and 397 MMbbl NGLs [91 million m3 oil, 235 billion m3 gas, 63 million m3 NGLs] (Table 5). The Labrador shelf is believed to have substantial gas resources, but to date discoveries have been small. The most promising areas for new discoveries are east and north of the Jeanne d’Arc basin where several deposits have been found (Fig. 2).

Table 5 Petroleum reserves and resources offshore Newfoundland and Labrador.

Equinor Canada’s proposed exploration drilling project in the Flemish Pass basin was approved in 2019 (Canadian Environmental Assessment Agency 2020a), but with the impact of Covid-19 on global oil demand and prices, these plans were in review in late 2020. Equinor Canada proposed drilling up to 24 offshore wells (six per exploration license) between 2019 and 2027.

In September 2020, three additional proposed projects by three different operators were under review by the Impact Assessment Agency of Canada: BHP Canada, Central Ridge and West Flemish Pass, all located approximately 350–375 km east of St. John’s, Newfoundland (Canadian Environmental Assessment Agency 2020b). The first step of federal environmental assessment is a public consultation process and environmental evaluation. After the consultation process and environmental review is completed, if the economic and operator conditions (e.g., corporate budget) are still suitable, wells will be drilled in accordance with the drilling plans.

Development Trade-offs

Development Plan

The number and type of development well are key design parameters in every offshore development. Engineers determine how wide wells should be spaced without suffering any significant loss of reserves. Major fields will usually have many productive fault blocks and numerous pay sands and require dozens of wells to develop. Reservoir sands that are deep and compact will require a smaller number of wells than a thin reservoir that is spread over a large areal extent. If there are faults and reservoirs are isolated, more wells will be required to reach these locations. Development drilling will occur throughout a field’s life as producing zones are plugged back and sidetracks drilled. Phased developments are often the preferred strategy for complex reservoirs or where the operator wants to limit initial development costs. The depletion plan of some developments may feature wells whose service changes during the life of the field, e.g., production wells converting to injection wells, water injection wells converting to gas injection, and in a few cases, delineation wells repurposed for development.

Development wells are more complex than exploration wells and usually more expensive to drill, not only because of their trajectories but because they must be completed (readied for production), and for complex completions cost can be as large as drilling. Horizontal wells, usually defined by an angle at least 80% to the vertical, typically cost at least twice as much as vertical wells per meter. Three-dimensional and extended reach wellFootnote 17 cost may be up to five times as much as a directional well of the same length. Most offshore development wells drilled from a platform rig are directional, and because many wells are drilled in sequence, learning occurs, and performance typically improves.

Dry Tree vs. Wet Tree Wells

A dry tree well has its treeFootnote 18 above the waterline and is accessible from the platform, allowing direct access from a platform rig or MODU. Production from dry tree wells flows from the reservoir through the conductor to the rig floor. Wet (subsea) wells have their trees located on the seafloor, either directly below the platform or offset from the platform. In iceberg-prone areas in water depth less than 100 m, wet wells are placed in excavated glory holesFootnote 19 to protect the wellheads and trees from scouring icebergs (Fig. 18). A MODU is needed to access subsea wells, and flowlines/risers are used to transport production to the facility for processing.

Figure 18
figure 18

Source: SUT 1998

Cross section of glory hole at Terra Nova.

There is no subsea infrastructure cost for dry tree wells but major construction and completion challenges to overcome in reaching target using directional and extended reach wells. Dry tree wells allow easy access for maintenance and repair, as well as for future sidetracking operations. In comparison with wet tree wells, dry tree wells have lower life cycle operating cost and can extract more resource because of the ability to intervene in the well on an as-needed basis at minimal cost (Reid et al. 2013).

Subsea wells are more expensive to equip, workover, operate, and decommission than dry tree wells and will be abandoned at a higher production rate, for all things equal, because of the back pressure that arises delivering the fluid to the host and less frequent interventions to maintain the well’s productivity. For empirical data on the difference between dry tree and wet tree economic limits in the deepwater US Gulf of Mexico, see Kaiser and Narra (2019). Subsea wells also have greater difficulty flowing with high water cuts because of hydrate formation, and if gas lift or subsea compression is used to flow to a lower abandonment pressure, flow assurance issues may result.

For subsea wells, the number and location of drill centers is a compromise between drilling operations, flow assurance, subsea cost, and future development. Access to the wellbore is only available from a MODU mobilization, which is expensive and can hinder reservoir development. Flow assurance is a significant operational issue and complication since fluid must be transported along (or underneath) the seafloor in flowlines to reach the host. Flow assurance requires use of chemicals, electrohydraulics for control, and regular pigging operations that increase operational cost and complexity. All reinjected fluids must also be transported in flowlines along the seabed.

GBS vs. FPSO

A gravity-base structure is a structure capable of withstanding the environmental forces to which it is exposed during its lifetime by its own weight. Gravity platforms may be built of concrete or steel or a combination of the two, but most of the gravity structures constructed for oil and gas development are concrete and are stabilized by skirts that penetrate the seabed. Concrete GBSs have a large footprint to minimize soil-bearing loads and, to provide buoyancy for transportation, have large enclosed volumes which can be used to store oil and other liquids. GBS developments in an iceberg environment are designed to withstand icebergs up to a specific mass limit (Widinato et al. 2013) and minor coverage of pack ice; if pack ice coverage is prevalent and thick, a protective berm or similar requirement will be needed like at Kashagan (Kaiser 2021).

Most GBS designs have a base caisson for oil storage and shafts penetrating the water surface to give support for the topside structures, and to serve for drilling, risers, and utility systems for offloading and ballast operations. In the first generation of GBSs, grout was normally placed under the platform to secure full contact between underside and seabed, but in the second generation of GBSs, more sophisticated systems were employed including potential refloat (Hjelde 2004).

FPSO facilities comprise a ship-shaped vessel held on location by a mooring system anchored to the seabed. If an FPSO operates in a hurricane or iceberg-prone area, the vessel may be specified with a disconnectable turretFootnote 20 to allow the FPSO to disconnect from its wells and move offsite. Well fluid is transferred using flowlines and risers and is processed by equipment mounted on the deck. Produced oil is stored in tanks in the hull, awaiting transfer to shuttle tankers through an offloading system. If water and gas injection is employed, it will be treated onboard the vessel and then transferred via risers/flowlines to the reservoir.

The most important distinction between GBS and FPSO development concepts is how drilling is performed. GBS developments allow the use of dry tree wells drilled and completed from a platform rig and can also use wet wells if reservoir targets are beyond the capability of the platform rigs, whereas FPSOs do not allow drilling (or workovers) from the vessel and require subsea (wet tree) wells drilled and completed from a MODU. A GBS for drilling can be used in conjunction with an FPSO to obtain the benefit of dry tree wells.

Subsea facilities at each drill center incorporate manifold systems to comingle the flow from the production wells, distribute gas lift to the production wells, and distribute water and produced gas to the water and gas injection wells. Divers and/or remotely operated vehicle (ROV) technology with marine vessels are used for maintenance, repair, and retrieval of the subsea production system.

Subsea chemical injection is achieved using umbilicals from the host transporting methanol, scale inhibitor, asphaltene inhibitor, and wax inhibitor/dissolver to the drill centers. Methanol is normally injected at the Christmas tree, while production chemicals can be injected either at the tree or downhole. Deaerated seawater is injected into oil zones for pressure maintenance. Electrohydraulic umbilicals to each manifold convey the required hydraulic fluid, chemicals, power, and communication signals necessary to operate the tree valves and monitor downhole and tree-mounted instrumentation.

Projects

Hibernia

The Hibernia field was discovered in 1979 and delineated by nine wells over 5 years (Smith 1997). The two main reservoirs, the Hibernia and the Ben Nevis/Avalon, are located at average depths of 3700 and 2400 m, respectively (Fig. 19), with the Hibernia reservoir estimated to contain over 80% of the recoverable oil. From the onset, the project was expected to require frequent wellbore intervention and extended reach wells, thus strongly favoring a GBS development despite higher investment cost (Elsborg et al. 2005).

Figure 19
figure 19

Depth chart of Hibernia and Ben Nevis reservoirs at the Hibernia field development

The Hibernia GBS is a cylindrical concrete caisson that extends from the seabed to 5 m above the waterline and designed to resist an iceberg impact up to 6 million tonnesFootnote 21 (Fig. 20). Four shafts extend 26 m above the caisson to support the deck and topsides weighing 60,000 t. The platform stands 224 m high, which is half the height of New York’s Empire State Building (449 m), and topsides facilities allow simultaneous drilling and production. Accommodations are for 185–270 personnel (Table 6).

Figure 20
figure 20

Source: SEC

Hibernia field development and offloading system schematic.

Table 6 Offshore Newfoundland production facility equipment capacity.

A 15-m thick ice wall forms the perimeter of the caisson and has 16 teeth designed to dissipate the impact energy of an iceberg to an interior tie wall (Fig. 21). The cells of the wall are filled with sea water and solid ballast. There are two drill shafts, a riser shaft, and a utility shaft; the utility shaft is permanently dry. The shafts are connected with walls and compartmentalize the interior of the caisson into six oil storage cells of 207,000 m3 (1.3 MMbbl) capacity.

Figure 21
figure 21

Source: Hoff et al. (1994)

Ice belt, shafts for drilling and utilities, and oil storage compartments.

The Hibernia Southern Extension is a subsea development about 7 km southeast of the GBS that included five production wells and six water injection subsea wells for pressure support. The production wells were drilled from the GBS platform rigs, and the injectionFootnote 22 subsea wells were drilled by a MODU.

The Hibernia reservoir is highly faulted and consists of multiple, stacked fluvial channels and sand bars. A total of 64 well slots are available, and circa 2020 almost all of these were in use (Fig. 22). Most fault blocks have been developed with remaining targets including smaller blocks and infill well opportunities (Lawrence et al. 2013). At the time of drilling, Hibernia wells expanded the extended reach envelope of the industry and continue to expand the envelope as shown in Figure 23 (Woodfine et al. 2011). Drilling cost generally increases with HD/TVD ratio, but many other factors are also involved in well construction cost (Kaiser and Pulsipher 2007).

Figure 22
figure 22

Source: C-NLOPB

Hibernia field well locations, Hibernia reservoir. Faults on Hibernia top L3b sandstone.

Figure 23
figure 23

Source: Hibernia Management and Development Company

Extended reach drilling at Hibernia circa 2011 relative to world database showing total vertical depth versus horizontal displacement in meters.

A combination of water flooding and gas reinjection is used to maximize recovery and is common to all projects in the region. Oil is transferred from the platform to shuttle tankers via an offshore loading system which consists of subsea pipelines, a subsurface buoy, and flexible loading hoses. Two tankers with a cargo capacity of 850,000 barrels (135,000 m3) are used to ship crude directly to market or to a transshipment terminal located in Placentia Bay, Newfoundland.

Terra Nova

The Terra Nova development is based on subsea tieback wells drilled in excavated glory holes and tied back to a double-hulled ice-strengthened FPSO vessel using flexible flowlines/risers (Fig. 24). Four drill centers called North West (NWDC), South West (SWDC), North East (NEDC), and South East (SEDC) are employed, each approximately 5 km away from the FPSO (Fig. 25). The colored lines in Fig. 25 indicate the type of flowline as production, gas lift, water injection, gas lift. The SE drill center is for water injection only (Haugen et al. 2007).

Figure 24
figure 24

Source: Suncor

Terra Nova development schematic with subsea tiebacks and glory holes.

Figure 25
figure 25

Source: Suncor

Terra Nova subsea layout.

The field is divided by faults into more than two dozen connected tank units, and most units or fault blocks hold an injector–producer well pair (Stephens et al. 2000). Most of the producer wells are deviated, and most injectors are vertical or close to vertical (Fig. 26). Three long reach wells have 4–5 km offset and 6–7 km measured depth.

Figure 26
figure 26

Source: Suncor

Terra Nova major fault blocks.

The FPSO vessel has a length of 292 m, a beam of 45.5 m, and a depth of 28.2 m (Lever et al. 2001). The mooring system consists of nine anchor legs in 3 × 3 arrangements, each group 120 degrees apart. The FPSO has five 5 MW thrusters, two at the bow and three at the stern, for position location and offsite movement.

The turret mooring system was designed to maintain station in the 100-year storm and to be disconnectable to avoid collision with icebergs with a mass greater than 100,000 t or pack ice greater than 5/10 coverage and 0.3 m thick (Howell et al. 2001). A controlled disconnect can be accomplished in waves up to 7.5 m significant height in 4 h, with all risers flushed and depressurized. An emergency disconnect can be accomplished in 15 min.

The turret is 70 m from the bottom of the spider buoy to the swivel stack (Fig. 27), and once the FPSO disconnects, the mooring and riser system is supported by the spider buoy at 35 m below sea level. At the main deck, the turret diameter is 12 m and at the vessel keel 22 m. When the spider buoy is released from the lower turret, it free-falls to its design depth.

Figure 27
figure 27

Source: Suncor

Terra Nova turret general arrangement.

White Rose

The White Rose development employed an FPSO facility, like that selected for Terra Nova, with glory holes and a disconnectable turret (Norman et al. 2008). Initial development required 14 production wells in the South Avalon reservoir and 11 water and gas injection wells (Pardy et al. 2013). Produced associated gas minus gas lift and fuel gas is reinjected into a gas cap in the northern part of the field to maintain reservoir pressure and for possible future extraction. The Northern pools and West Avalon extension has a thick gas accumulation and a thinner, less extensive, oil leg (Fig. 28).

Figure 28
figure 28

Source: White Rose DA volume 2 (development plan)

White Rose complex Avalon pools.

The West White Rose project was proposed to access resources in the West Avalon pool using a concrete gravity wellhead platform produced back to the FPSO. The wellhead platform would host a drilling rig intended to improve drilling efficiency, lower operating costs, and extract a larger portion of the resource, but the project is currently suspended and future operations under review. If sanctioned, the concrete GBS is expected to be 145 m high and weigh 210,000 tonnes, with total platform height 241 m and operating weight 30,000 ton.

Hebron

After initial discovery in 1980, field delineation and appraisal stretched over a period of 19 years before the decision to proceed was made in 2012 with a concrete GBS and offloading system (Fig. 29) (Wolfe et al. 2018).

Figure 29
figure 29

Source: Hebron DA volume 2 (development plan) September 2011

Hebron drilling, production and storage gravity-base structure.

Three rotated fault blocks define the structural framework of the Hebron field (Fig. 30). Within the three main fault blocks are three main reservoirs, and five hydrocarbon pools define separate accumulations (Cornaglia and McNeill 2018). The initial development phase focuses on the Hebron fault block and its three vertically separated reservoirs Ben Nevis (Pool 1), Hibernia (Pool 5), and Jeanne d’Arc (Pool 4).

Figure 30
figure 30

Source: Hebron DA volume 2 (development plan) September 2011

Schematic cross section across the Hebron project area.

The largest reservoir is the Hebron Ben Nevis reservoir unit (Pool 1) and accounts for 80% of the total recoverable project reserves. Hebron Ben Nevis reservoir oil is 20° API, and it is significantly denser than Hibernia crude. The Hebron Hibernia reservoir (Pool 5) and Hebron Jeanne d’Arc reservoir (Pool 4) are of higher quality than Hebron Ben Nevis but more difficult to access. The Ben Nevis reservoir (Pool 3) is expected to be developed as a subsea tieback at a later date.

The Pool 1 Ben Nevis reservoir is the focus of the development and requires extended reach producers drilled from the platform and completed with up to 1500-m open-hole gravel packs to mitigate sand control issues. A series of peripheral water injectors is used in development, and solution gas will be stored in Pool 2 Ben Nevis reservoir and produced again later in field life when gas requirements exceed production from the field. The deeper Pools 4 and 5 will be developed at a later stage but are not expected to contribute significantly to total production.

Hebron’s upper wells encounter degraded reservoir properties, while the lower wells are located in the best part of the reservoir but closer to the oil–water contact, exposing them to a higher risk of early water breakthrough. To mitigate the water production rate uncertainty, the facilities were designed with robust water handling capability.

Development Cost

Economic Measure

Unit development cost provides a rough indication of the economic viability of a project and is a useful metric to compute prior to more advanced cash flow modeling (Gallun et al. 2001). There are several ways to compute unit development cost, but probably the most common method combines estimated total capital spending plus operating costs over the production life cycle divided by the expected ultimate recoverable reserves (EUR):

$$\frac{{\hbox{Capital\,spending}} + {\hbox{Operating\,expenditures}}}{{\hbox{Expected ultimate recoverable reserves}}}. $$

All quantities in both numerator and denominator are expected values at the time of evaluation, usually project sanction or near the start of production, but can also occur later when better estimates are available. Capital spending and operating expenditures are usually not discounted, but for comparisons, inflation adjustment is suggested.

Exploration costs are sunk costs and are usually not included in development cost metrics. EUR is usually interpreted as initial proved plus probable reserves (2P) estimated using P50 probability. At the start of development, 2P reserves and life cycle cost are uncertain, but with the passage of time both become better known. Near the end of production, EUR and cumulative production coincide.

On a regional level, Newfoundland unit development cost through 2020 based on the aggregate inflation-adjusted data described in the Introduction yields:

$$\frac{{\left( {\$ 33 + \$ 30} \right)\,{\hbox{billion}}}}{{1.94 \,{\hbox{Bbbl}}}} = \$ 32.5/{\hbox{bbl}} $$

Life cycle development cost applies total reserves and an assumed additional $10 billion in future production costs to yield:

$$\frac{{{\left( {\$ 33 + \$ 30 + \$ 10} \right)\,{\hbox{billion}}}}}{{{3.3\, {\hbox{Bbbl}}}}} = \$ 22.2/{\hbox{bbl}}. $$

At a project level, total capital and operating costs estimated by operators at the time of project sanction and adjusted to 2019 ranged from $4.8 billion at White Rose to $16.6 billion at Hebron (Table 7). The capital expenditures for GBS structures are two to three times greater than FPSO vessels. For Hibernia, life cycle operating cost is less than half of capital cost, but for Hebron, costs escalated to over two-thirds capital cost. Larger projects with greater reserves are expected to have lower unit development cost, but variability is large (Table 8). Unit development cost ranged from $8/bbl (Hibernia) to $24/bbl (Hebron).

Table 7 Capital and operating cost estimates in million Canadian dollarsa at time of project sanction and inflation adjusted to 2019
Table 8 Unit cost metrics inflation-adjusted to 2019.

Spending Plans

Operators sometimes report capital spending and operating cost estimates in development plans submitted to regulators. In the absence of better information, these data may be matched against actual activity levels, but appropriate caution should be exercised in interpreting results since this is a gross approximation based on unverified data that is potentially unreliable.

For example, comparing White Rose capital spending estimates shown in Table 9 with the actual number of wells drilled during the time period leads to an inferred cost of $35 million per development well (unadjusted) and a life cycle production cost (excluding transportation cost) of $4.2/bbl. These well cost estimates are about two to three times less than the actual development costs shown in Table 2. Hebron operating expenditures shown in Table 10 leads to a production cost estimate of $9.8/bbl.

Table 9 White Rose development capital and operating cost estimates.
Table 10 Hebron platform development capital and operating cost estimates.

ExxonMobil reported capital and expenditure cost for the Hebron GBS development and for the Pool 3 subseaFootnote 23 development (Table 11). Total construction cost for the GBS was estimated at about $6.5 billion, development wells cost $1.9 billion, and life cycle production cost $5.9 billion. Using this information, along with the reported/expected 19 producing wells and 7 gas/water injection wells required in initial development, leads to an average unadjusted development well cost of $73 million ($1900 million/26 wells).

Table 11 Hebron costs with Pool 3 development in million dollars.

Employment

Labor

Labor costs in offshore oil and gas operations are a significant expense (Kaiser 2019). Labor costs include the salary of employees who are directly involved in production activities, services such as general repairs and maintenance, and supervision. Payroll and benefits for corporate staff are usually not included, but employee benefits, such as insurance and medical service, may be included (Gallun et al. 2001). Some benefits are required by local laws and benefit packages vary by company.

All producing facilities offshore Newfoundland are manned 24 h a day by two crews working on 12-h shifts on a 14- or 21-day schedule. During well intervention and drilling operations or significant upgrades, head counts will increase. Personnel represent a significant fixed cost associated with production and influence many other cost components such as personnel logistics and catering.

Head Counts

Operators are required to file an annual benefits report to C-NLOPB summarizing employment for operations and construction separately. At the end of 2019, the head count for oil and gas operations offshore Newfoundland totaled 4520—Hibernia had a head count of 1400, Terra Nova 853, White Rose 1105, and Hebron 1162 (Table 12). Reported persons are directly employed and include operator and contractor personnel. Personnel are typically organized into different groups such as field management, production crew, multi-skill personnel such as mechanics and electricians, roustabouts, housekeeping, and catering. Construction activity ceases with the start of operations.

Table 12 Project employment as of December 31, 2019.

Year-end head count differs from full-time equivalent data reported as person-hours because it represents a point in time as opposed to all employment activity over the full year. Onshore staffing and support for offshore operations is about the same size as offshore requirements for each producing field.

Person-Hours and Head Counts vs. Production Expenditures

In 1997, about 1.6 million person-hours were required in operations, which increased to about 5.3 million person-hours in 2017–2018 as more facilities have been installed. As one might expect, production expenditures relate to person-hours worked (Fig. 31), and robust relationships hold at individual fields using head counts (Fig. 32).

Figure 31
figure 31

Source: C-NLOPB

Total production expense and operations person-hours at Newfoundland’s offshore developments, 1997–2017.

Figure 32
figure 32

Source: C-NLOPB

Production expenditures in million dollars and head counts at the end of each reporting period; Hibernia (top), Terra Nova (middle), and White Rose (bottom), 2006–2018.

Roughly speaking, at a regional level about one-third of total person-hours worked per year approximate annual expenditures in million dollars. For producing fields, about 40 to 50 percent of total head count approximates operator expenditures in million dollars:

ExpendituresNF = 0.37 · Person-hours, R2 = 0.87.

ExpendituresHib = 0.47 · Head count, R2 = 0.75.

ExpendituresTN = 0.47 · Head count, R2 = 0.54.

ExpendituresWR = 0.42 · Head count, R2 = 0.87.

Labor Contribution to Production Expenditures

Using 2020 workforce levels, and assuming salaries of $200,000 for management, $150,000 for engineers, marine crew, and skilled trades, and $100,000 for all other employees yields a total labor cost of about $595 million, about 25% of the total production expenditures in 2020.

Production Cost

Operating Cost vs. Capital Expenditure

Capital expenditures (CAPEX) represent the investment required to design, construct, and commission the hardware for field development, and include the wells, platforms, facilities, equipment, pipelines, and everything else with a lifetime greater than one year. CAPEX is typically defined as those items whose useful life exceeds one year, and as such, tax regulations require each item be depreciated on a specific schedule when computing net income (Gallun et al. 2001). In contrast, operating expenditures (OPEX), also referred to as lease operating expenses, lifting cost or production cost, represent items whose useful life is one year or less and costs are expensed for accounts.

Unlike capital expenditures, operating cost is generally much less transparent, and public data come in widely different forms and quality (Kaiser 2019). Site-specific attributes need to be accounted for, most of which are not observable or known, and can only be inferred with a high degree of uncertainty. The North Sea, both the UK and Norwegian sectors, is a notable exception and provides reliable and transparent offshore operating cost data. Newfoundland production cost is much better than the U.S. Gulf of Mexico, but not as good as the North Sea because of mixing issues described below.

For offshore development, most capital expenditures occur upfront in the exploration and development stage, with facility construction/installation and development well drilling, whereas operating costs start at first production and run through the life cycle of the field. For developments where drilling requires a structure to proceed, such as occurs with GBSs, significant drilling cost will be incurred after first production. Because OPEX occurs over a longer period compared to CAPEX and its annual amounts are small in comparison, its impact to profitability is usually less significant than the schedule and cost overruns that impact CAPEX and the changes in commodity prices that occur over the life of the asset.

Unit Operating Cost

Production cost is usually defined as lifting cost plus gathering and transportation costs and may or may not include production taxes (Gallun et al. 2001). These costs are all short term, less than one year in duration, and incurred in operations. Since gathering and transportation costs and production taxes are often small on a relative basis, their inclusion or exclusion will usually not significantly impact the metric. Formally, unit operating cost is calculated as the ratio of annual operating cost divided by annual sales production on a boe or Mcfe basis:

$$ {\hbox{Unit cost}}\;\left( {\$ /{\hbox{boe}}} \right) = \frac{{\hbox{Direct\,operating\,cost}}\;(\$)}{{\hbox{Sales production}}\;({\text{boe}})}.$$

If sales are exclusively or predominately oil or gas, primary production units are employed. Life cycle unit operating cost is computed using the same formula but on a cumulative undiscounted basis.

Normalized Production Expenditures

C-NLOPB assigns all expenditures after first production to the production cost category which is problematic from an accounting perspective since expenditures for both short-term and long-lasting items (e.g., new wells) are mixed, and because of this mixing of cost categories, the estimated unit production cost will be higher compared to the standard use of the term.

Using the C-NLOPB categorization, inflation-adjusted production cost averaged $23.4/bbl from 2006 to 2018 and varied from $16.8/bbl at Hibernia, to about $36/bbl at Terra Nova and White Rose/North/Amethyst (Table 13; Fig. 33). Standard deviation of production cost during this time was $9.6/bbl. Composite averages are smaller, from $15.8 at Hibernia, $27.0 at Terra Nova, and $34.2/bbl at White Rose/North/Amethyst. Production cost at Terra Nova and White Rose is more than twice as large as Hibernia reflecting the primary difference between GBS and FPSO developments. Differences in operations personnel, maintenance, and chemical needs to support subsea wells are greater than dry tree wells.

Table 13 Average inflation adjusted production cost statistics offshore Newfoundland, 2006–2018.
Figure 33
figure 33

Source: C-NLOPB

Production cost at Newfoundland’s offshore developments include capital spending on development wells drilled after first production. White Rose/North Amethyst production cost in 2018 is not reported since the statistic falls significantly outside of the graph bounds.

A better estimate of Newfoundland production cost requires that the capitalized items in production expenditures be estimatedFootnote 24 and excluded from the metric.

Life Cycle Operating Cost and Development Well Cost Relationship

To estimate operating cost according to its standard formulation (i.e., no capitalized expenditures), capitalized items in the production expenditure category must be estimated and excluded from the metric. Development wells are believed to be by far the largest and most important capitalized cost in C-NLOPB’s production expenditure category, and thus the focus of the adjustment.

If production cost at each field was known, average development well cost could be estimated, and vice versa, if development cost was known, average production cost could be estimated using the average well cost relationship:

$$\frac{\hbox{Production\,expenditure}\,(\$) - \hbox{Operating\,cost}\,(\$/\hbox{bbl})*\hbox{Production}\,(\hbox{bbl})}{\hbox{Number\,of\,development wells}}.$$

In Table 14, a theoretical relationship between life cycle operating cost and average well cost using this relation is depicted. Enter the column at the left at the assumed average production cost and read off the row entry for the average development well cost for the field. For example, at Hibernia, if average life cycle production cost is $8/bbl, then average development cost is estimated at $64 million/well. Similarly, if average production cost was $18/bbl at Terra Nova, then average development well cost would be $119 million. The different sensitivities at the three fields are the result of different field characteristics. If one enters the tableau from the right at the assumed average development well cost, life cycle production cost can be estimated continuing leftward. For example, if average development well cost at Terra Nova is $70 million (Table 2), then average production cost would be estimated at about $21/bbl.

Table 14 Theoretical relationship between life cycle operating cost and development well cost offshore Newfoundland

Adjusted Production Cost

At Hibernia and Hebron, assuming $40 million per development well, development well expenditures of $6.2 billion were allocated to production cost. At Terra Nova and White Rose/North Amethyst, assuming $60 million per development well leads to $3.2 billion allocated to production. In total, of the reported $25.8 billion production expenditures from 1997, $9.4 billion is estimated to arise from development drilling, leading to $16.4 billion adjusted cost, or an adjusted cost of $8.5 per barrel produced. If development wells cost on average twice as much as assumed, $18.8 billion would arise from development drilling, and adjusted production cost would be $7 billion, or about $3.7 per barrel.

Conclusions

Offshore Newfoundland is characterized by severe storm and sea conditions, including the presence of icebergs, which challenge all aspects of exploration and development. Developments in extreme environments can be commercialized and performed in an environmentally responsible manner but require careful oversight by regulators, large investments by operators, and long development cycles to bring to fruition. Newfoundland waters are one of the most challenging offshore environments worldwide and require investors to take large economic risks in development, but Canada’s transparent and stable political regime, rule of law, and favorable fiscal terms balance the equation and have encouraged investment in the region.

From 1966 to 2019, operators have spent a total of $84 billion Canadian dollars in exploration, development, and production activities offshore Newfoundland and Labrador, approximately $15 billion in exploration, $36 billion in development, and $33 billion in production. Four major projects have been developed offshore Newfoundland, and since production started in 1997, operators have produced about 2 billion barrels of an estimated 3.3 billion barrels recoverable oil.

From 1998 to 2018, exploration and delineation drilling averaged $90.9 million per well, and development wells drilled from MODUs were nearly identical at $91.1 million per well. Both exploration and development wells were drilled from MODUs, so perhaps the similarity in results are not that surprising. The average injector well cost slightly less at $68.8 million per well. On a per meter basis, exploration and delineation drilling cost $26,500 per meter compared to $15,900 to $24,000 per meter for development wells.

On a regional basis, development expenditures normalized by cumulative production was $32.5/bbl since the start of production and is expected to fall to $22/bbl when recoverable reserves have been extracted. Average inflation-adjusted production cost from 2006 to 2018 was estimated at $23.4/bbl and ranged from $16.8/bbl at Hibernia to about $35/bbl at Terra Nova and White Rose.