Introduction

The northern part of Australia is known for its high insolation levels, favourable conditions for wind farms and immense availability of land offering an attractive environment for large utility-scale renewable developments. Recently, a few ambitious projects were proposed by developers to leverage this Australian renewable energy potential to generate and export clean electricity to Southeast Asia through a subsea high voltage direct current (HVDC) interconnector. Singapore was selected as the receiving country given its strategic location within Southeast Asia and its high reliance in fossil fuel for power generation. Further, this tie-in location would enable Australia to be connected to the future Asian Super Grid [1], currently at the feasibility stage, interconnecting most Asian countries in the long term. This paper presents a credible technical definition of an Australia—Singapore interconnector with the current technology, in terms of configuration, cable cross-section design and marine route to enable an overall project assessment and to quantify the unique challenges from a transport and installation, and cost perspectives.

Southeast Asia electricity status

Power generation in Southeast Asia is dominated by fossil fuels. Amongst the eleven Southeast Asian (SEA) countries, the combined annual electricity consumption of Indonesia, Malaysia and Singapore represents about 50% of SEA power consumption, and these three countries are responsible for 57% of CO2 emissions from the SEA power generation system, the power carbon footprint from these countries are presented in Table 1.

Table 1 Carbon intensity (2019) [2]

Typical carbon emissions of coal, oil and natural gas fired plants are 1000, 800 and 450 gCO2/kWh, respectively; whereas renewable energy generations such as photovoltaic (PV) solar, wind and hydropower present a carbon intensity of 40, 12 and 4 gCO2/kWh, respectively. Singapore is located at the centre of SEA power consumption with a fast-growing economy and population and it is forecasted that the power demand will further increase. The power generation system in Singapore is almost exclusively reliant on natural gas with 95% of electricity produced coming from gas-fired plants. Since 2013, Singapore has met their gas demand by importing through pipelines from Indonesia and Malaysia; this raises energy security concerns. In 2013, this high dependence was reduced with the construction of a LNG (liquefied natural gas) terminal at Jurong (west side of the island) to enable supply from LNG producers; in 2019, the country’s gas imports included 30% LNG versus 70% from piped natural gas.

Singapore has very limited renewable energy resources available. Located within the intertropical convergence zone, Singapore is characterised by a relatively windless and cloudy weather regime that effectively precludes wind energy and offers only moderate solar potential that is ostensibly limited to small-scale rooftop solutions due to the city-state’s land scarcity (that said, some marginal floating solar farms have been developed on inland water reservoirs).

Although natural gas is the cleanest fossil fuel, power generated exclusively with gas-fired plants remains a high-carbon content source. The potential for a long HVDC subsea interconnector is one of the few credible options to lower Singapore’s emission levels, while being highly suitable for integration into the centralised nature of the country’s power system and strengthening energy security. Moreover, the political stability creates favourable conditions for the development of long-term capital-intensive HVDC projects.

HVDC interconnector

Background

Subsea HVDC interconnectors have gradually increased in power capacity and length over the last 50 years, playing an increasingly strategic role in transnational grid connections. These power links have enhanced countries’ energy security, fostered international collaboration in the power sector, and, more recently, eased the integration of intermittent renewable energy sources. The Gotland HVDC link, built in 1954, was the first HVDC subsea cable, 50 km in length, connecting Gotland island to mainland Sweden and operating at 100 kV with a 20 MW power capacity. Today, subsea HVDC cable is a mature technology with approximately 10,000 km of cables currently in service, predominantly deployed in Europe (more than 70%) where most of the manufacturing facilities are located. Latest developments enable fabrication of subsea power cables rated to 600 kV and delivering capacity up to 1200 MW. A sample of some of the World’s longest interconnectors, either in service or currently in construction, have been short-listed and presented in Table 2.

Table 2 Sample of some of the World’s longest interconnectors [4]

Interconnector configuration

Interconnectors can be configured either in monopolar or bipolar modes.

A monopolar interconnector is composed of a single conductor of negative polarity and uses earth or sea as the current return path. Alternatively, a concentric metallic return can be incorporated within the cable cross section or a separate cable dedicated to the metallic return is routed parallel to the conductor cable.

A bipolar link includes two separate conductors in opposite polarity. There are actually three types of bipolar link: “rigid bipole” without any return path, bipole with earth return and bipole with metallic return (through a separate cable). The most appropriate solution for this long interconnector will be a bipolar configuration with earth return comprising two parallel subsea cables, typically laid 50–500 m apart along a defined route. The main advantage of this bipolar interconnector arrangement is the ability, in the event of one cable failure, to convert the intact cable into monopolar mode with earth return over the repair duration, allowing half of the electricity capacity to be transmitted. Further, the existing HVDC technology is qualified for cable with power capacity up to 1.2 GW. To meet the expected interconnector power capacity, between 2 and 3 GW, the interconnector shall be configured in bipolar mode.

For the purpose of this study, two individual HVDC subsea cables of 1.2 GW capacity each have been considered resulting in an interconnector power capacity of 2.4 GW.

HVDC cable cross-section design

The structure of HVDC subsea cables includes a central conductor surrounded by an insulation, armouring and external sheath. Additional elements such as tape and screens are used to interface between the various layers (Fig. 1).

Fig. 1
figure 1

(Source Europacable)

HVDC submarine cable

Conductor material

HVDC conductors can be either made of copper or aluminium (Fig. 2). Historically, copper has been the conductor material of preference due to its high conductivity, minimising electrical losses, and good corrosion resistance properties. However, aluminium has been increasing used as conductor material to take advantage of the weight and cost reductions. Aluminium density is about only a third of copper density (2700 kg/m3 for aluminium versus 8300 kg/m3 for copper) resulting in lighter HVDC cable designs; this is attractive for deepwater application to reduce catenary loads during cable laying operations. Furthermore, the copper price rose significantly over the past two decades and considering an aluminium conductor offers procurement cost savings; presently, aluminium is three times less expensive than copper. Because of aluminium lower current carrying capacity, aluminium conductors have larger cross-sectional area compared to copper conductors to meet similar electrical performances; resulting in an increased HVDC cable diameter which may exacerbate packing and logistic issues.

Fig. 2
figure 2

Typical HVDC cable designs—copper conductor with XPLE insulation (left) and aluminium conductor with MI insulation (right) (source Prysmian)

For this project, it is anticipated that the interconnector will be made of different designs along the route, most likely a design including a copper conductor for the shallow water sections and an aluminium conductor for the deepwater sections to minimise the lay tension during installation.

Cable insulation

Two different insulation technologies exist for subsea HVDC cable: mass impregnated (MI) and cross-linked polyethylene (XLPE).

Mass impregnated insulation consists of multi-layer paper tapes, impregnated with a high viscosity oil-like compound, helically wrapped around the conductor to reach the desired insulation thickness. Mass impregnated cable has an extensive track record for high voltage cables, with operational voltage up to 600 kV. MI cable can be used with both line commutated converter (LCC) and voltage source converter (VSC) HVDC technology with proven track record. However, MI cable is a declining technology due to its low operating temperature (typically limited to 50 °C), diameter, weight, and cost compared to XLPE cable technology.

XLPE cable includes an extruded isolation around the conductor made of polymer and able to withstand operating temperatures up to typically 90 °C for HVAC and 70 °C for HVDC (higher temperatures are being qualified by suppliers). Extruded XLPE isolation has been extensively used for HVAC cables with voltage ratings up to 500 kV. The highest voltage of HVDC XLPE cable currently in service is 320 kV; however, ongoing technology developments focus on increasing the voltage capability and a XLPE cable rated for 525 kV has recently been successfully qualified [13]. XLPE cable is not compatible with voltage polarity reversal required with LCC HVDC converters. The recent increased application of VSC HVDC converters has created a growing demand for HVDC XLPE cables.

Presently, only MI cable is qualified for the intended purposes. However, the timeline of such long interconnector project typically spans over a decade or more and it is expected that XLPE will become a viable option for a 500 kV HVDC cable during the execution of this project.

Armouring

Armouring is made of layers of individual steel wires to provide the mechanical axial strength required during handling and installation operations. Generally, the armouring consists of a single layer or two layers in opposite pitch directions to offer a torque-balanced cable. Further, this armouring acts as a protective mechanical barrier against external damages from dropped objects, fishing activities or dragging anchors. The design parameters of the armouring include the number of layers, number of individual wires, lay pitch angle, wire diameter, wire material and grade.

External sheath

Outer sheath is made of synthetic yarns to offer sufficient grip during laying operation and provide general protection.

Preliminary cable characteristic

It is anticipated the cables will have multiple cross-section designs along the route, with different conductor materials, insulation technologies and armouring arrangements to account for constraints related to water depth, laying operation, seabed on-bottom stability and protection against external damage. The linear weight of this HVDC cable is anticipated to range between 40 and 60 kg/m; however, for the purpose of this assessment, the cable details have been assumed identical along the route with the following characteristics:

  • Cable voltage =  ± 525 kV

  • Power cable capacity = 1.2 GW (2.4 GW in total)

  • Outer diameter = 150 mm

  • Linear weight in air = 50 kg/m

Based on these assumptions, the total cable payload of this interconnector is 320,000 te.

The electrical loss through HVDC cable is approximately 3% per 1000 km. Hence, it is anticipated that total electrical loss through this interconnector will be approximately 10% for the subsea portion.

Route selection

Renewable energy projects within Northwest Australia

A few large-scale renewable energy projects located in northern Australia are currently in the feasibility phase, such as the 10 GW solar farm developed by Sun Cable in the Northern Territory and the 15 GW of combined solar and wind farms developed by the Asian Renewable Energy Hub in the Pilbara. These very ambitious developments intend to take advantage of the high insolation levels and favourable wind conditions to provide sustainable renewable power to the highly populated Southeast Asia in addition to the local mining industry. These projects include photovoltaic solar farms and wind farms in the order of 10 GW or more in capacity coupled with energy storage capacity stretching from the Pilbara in Western Australia (WA) to the Tennant Creek in Northern Territory (NT) (Fig. 3).

Fig. 3
figure 3

Region of Australia with large-scale solar and wind export generation potential

The interconnector can depart mainland Australia from various locations along the WA and NT shores stretching from Port Hedland up to Darwin, representing approximately 1500 km of coastline. For the purpose of this study, a marine route landing at Cape Londonderry, WA northernmost point, was arbitrary selected to minimise the subsea cable length. However, the landfall selection will depend on many parameters balancing the technical constraints and economic viability whist ensuring the least disturbance to the environment and to the traditional owners. Further, the construction and operational implications of the remoteness and isolated nature of the region will need to be assessed in detail during the landfall selection process. Furthermore, wind/solar farm sites and potential synergies across developments may influenced the chosen location.

Marine route

Xodus’ anticipated marine route (to inform this report) aims at minimising the overall cable length whilst avoiding the unnecessary deepwater and steep-sloped sections between Australia and Singapore. Hence, the subsea cable departs from the north of Western Australia towards the northwest, across the Timor Sea, runs south of Timor-Leste, reaches Indonesia through the Savu Sea, then the cable is routed between Bali and Lombok and runs through the Java Sea until reaching Singapore (from the island east side, within the Changi area).

The total route length is estimated to be 3200 km with water depths up to approximately 1900 m. The marine route can be divided in three main sections from a water depth perspective as presented in Table 3 and illustrated in Fig. 4.

Table 3 Marine route
Fig. 4
figure 4

Subsea cable route (from Australia to Singapore)

The first 400 km and last 1600 km, respectively, Sections A and C, lie in relatively shallow waters, typically 100–200 m deep, with a relatively flat profile. Conversely, the water depth along Section B varies significantly with alternate deep and shallow sections and high gradients. The deepest section is reached at the Timor Trough with a water depth of 1900 m and high slopes at either side. This report does not consider any detailed macro-routeing works to minimise this variability; it is anticipated this may be done to inform development of the project, particularly for site investigation survey specification.

Key challenges

Java Sea/Singapore Strait

The Java Sea is characterised by a relatively shallow and featureless seabed with an average depth of 46 m but it is highly congested. The interconnector would run across the Java Sea, from southeast to northwest, for approximately 1500 km. The key challenges along this route portion are related to the seabed congestion level, crossing a large number of existing pipelines and communication cables, and protection against damage from fishing activities that will necessitate the cables being trenched or protected by alternative means over an extended route length.

The Singapore Strait is known to be one of the World’s busiest waterways. Specific design considerations will be needed at the approach of Singapore to protect the cables against anchor damage and navigation hazards, in general. Further, current through a single HVDC cable in shallow waters may create navigation compass deviations of by-passing vessels. For a bipolar interconnector, bundling the two cables can minimise this issue as the magnetic effects of currents in opposite polarities act to cancel each other. It is anticipated the cable section on the approach to Singapore will require specific cable arrangement, protection, cross-section design and potentially operational restrictions (i.e. limited monopole mode allowed) to accommodate the high vessel traffic of the region (Fig. 5).

Fig. 5
figure 5

Indicative shipping traffic along the interconnector route [12]

Cable burial and protection

Subsea cables are exposed to various external hazards including fishing gears, ship dragged anchors (from emergency or accidental events) and dropped objects in addition to waves and sediment movements, particularly in shallow water, but consideration also needs to be given to seismic activity (slumping). The cable cross section may include additional armouring to enhance protection level, but the most common cable protection method is cable trenching where the cable is buried at a depth of typically 0.6–1.5 m below the seabed level. Cable trenching is performed using either a towed plough or a water jet where high-pressure water flow fluidises the seabed (typically used in softer soil condition) creating a trench. Both methods can be performed either simultaneously to cable laying operation or as a separate campaign after the cable has been laid on the seafloor. The protection philosophy and approach depend upon various parameters such as soil condition, cable length and risk profile of the product and, indeed, the owner. For this project, as expensive cable lay vessels (CLVs) will be involved, it is anticipated that a separate trenching campaign, potentially executed by multiple vessels, will be selected to avoid slowing down cable lay rate and to decouple, to a degree, laying and trenching schedules. The trenching rate of progress varies depending on the soil condition, required burial depth and selected equipment; it typically ranges from 100 to 400 m per hour. For the deepwater section (most of Section B), where the water depth typically exceeds 400 m, the external damage risk level is likely to be low (but depends upon fishing activity) and cables are typically surface-laid and not trenched. Considering the bathymetry along the interconnector cable route assumed in this paper, it is estimated that approximately 60% of route will require trenching or alternative protection.

Protection of cable at pipeline or cable crossing locations are different in nature and requires additional infrastructure such as rock placement, rock bags and/or concrete mattresses. External cast-iron shell or plastic cable protection systems may also be considered where two half shells fully encapsulate the cable to offer an additional level of protection; this equipment is normally installed on board the CLV prior to deployment.

Deepwater section—Timor Trough

Installation in deepwater

HVDC cable installation in deepwater has been performed in a few instances, such as the SAPEI project installed in 1600 m water depths, but presents its own set of challenges.

In more shallow water, power cables are commonly deployed using a horizontal lay system composed of caterpillar-type tensioners arranged on the CLV deck (either one or two in series). The tensioner(s), typically comprising 2, 3 or 4 tracks, each a few meters long, applies a squeeze force to the cable to withstand the weight of the catenary suspended in the water column during cable deployment. The cable is typically routed at the vessel stern and overboarded through a 90° chute.

Heavy cables deployed in deepwater result in high lay tensions that may compromise cable long-term integrity through ovalisation of cable insulation and/or lead sheath and excessive strain on the conductor.

Ovalisation of the installation occurs when the required tensioner squeeze force exceeds the cable crushing capacity. In this instance, a capstan wheel may be a suitable alternative to a tensioner and consists of an integrated wheel (typically 5 m in diameter) within the cable lay vessel deck around which the cable is wrapped (generally a few wraps) to withstand the lay tension through the capstan effect whilst distributing the side loading over a longer cable section, see Fig. 6.

Fig. 6
figure 6

Capstan wheel cable deployment in deepwater

The other main limitation of cables deployed in deepwater is the excessive strain level within the cable conductor and especially at any joint locations, between two delivered cable sections, where conductors are welded and inherently creating a localised strength capacity reduction. Cable deployment in deepwater is a governing load case to be accounted for in the design of the cable cross-section, and particularly through the armouring selection in terms of number of wires, wire diameter and wire material.

Assuming the cable details presented in “HVDC interconnector” with a linear submerged weight of 32 kg/m and a dynamic amplification factor of 1.25 (to account for vessel heaving) in 1900 m of water, the dynamic lay tension is approximately 80 te. As a contingency, the design should account for cable recovery. For this scenario, the recovery tension, accounting for friction/capstan effect over a chute in addition to the catenary load, is expected to be in the order of 100 te.

Repair Omega loop and route corridor

In the event of a cable failure during service, the repair procedure entails an extra cable length of approximately double the water depth at the repair location being laid on the seabed, typically, perpendicular to the initial cable route as an Omega or hairpin loop. A typical offshore cable repair procedure, after fault location, consists of the following steps:

  • Perform subsea cut of the existing faulty cable using a WROV.

  • Recover to deck the first cut end and spool back a sacrificial section, this may be a few hundred meters, to ensure the remaining cable is free of failure.

  • Perform the joint on installation vessel deck between the existing cable and the replacement cable.

  • Lay away the existing cable/replacement cable toward the second cut end of the existing cable (Fig. 7).

  • Recover the second cut end to deck whilst continuing to lay the replacement cable, spool back a sacrificial section and perform joint on installation vessel deck between replacement cable and existing cable.

  • Lay the two hanging cables sections using a laydown quadrant (Fig. 8) perpendicular to the initial lay route forming an Omega loop, also called a hairpin loop (Fig. 9). The adjacent sections within the loop are approximately 5 m apart (equals to the quadrant diameter) but certainly not less than the cable MBR.

Fig. 7
figure 7

Cable repair steps—replacement cable laying

Fig. 8
figure 8

Cable repair steps—laydown

Fig. 9
figure 9

HVDC cable route after repair—Omega loop

The selected cable route shall enable this repair procedure to be performed at any location along the interconnector. This requirement dictates the cable route to be included within a corridor, this corridor becoming wider as water depth increases.

Seismic region

Any interconnector project requires a deep understanding of the seabed to support the route selection. As illustrated in Fig. 4, the section crossing the south part of Indonesia (Section B) presents high seabed depth variations with significant slopes and slope gradients. It is anticipated for this specific project that geophysical and geotechnical surveys will be of upmost importance to enable an optimum route selection through this area which is also known for its high level of seismic activity. Cable integrity can be threatened by movement of undersea materials through slides, slumps or turbidity currents. Inherently, this risk is exacerbated in areas combining steep slopes and high seismic activity as sediment material movements are often triggered by earthquakes. Consequently, an understanding of the activity history by analysis of survey data along the selected route with considerations of dynamic route development during surveys is key to managing life-time asset risk.

Cable delivery

For such a large scope, it is anticipated that both cable manufacturing and installation will be awarded to multiple suppliers and contractors. The intent is to share the workload across various parties to achieve completion of cable fabrication and installation within a certain timeframe, typically within 2–3 years after cable fabrication has commenced. As such, the adopted strategy shall seek to minimise the risk of HVDC cable in storage for extended time periods (whether at the factory, on the quayside or, on the seabed awaiting the next installation campaign and final commissioning) due to concerns related to factory acceptance test (FAT) validity, cable integrity, preservation requirements, storage cost and insurance/legal matters.

Suppliers and locations

HVDC cable manufacturing requires specific know-how and capital-intensive plants; these plants are located in areas with well-established logistical infrastructures and marine access facilities. Globally, there are a limited number of HVDC cable suppliers and those with the longest track record and highest capacity are mainly based in Europe (Fig. 10). Nevertheless, a couple of potential suppliers are located in Northeast Asia and with increasing capability these may be attractive for this project. The list of HVDC cable suppliers and location is presented, in alphabetical order, in Table 4.

Table 4 Cable suppliers and manufacturing facility locations
Fig. 10
figure 10

HVDC cable manufacturing facility locations

For the purpose of this report, the plant locations have been grouped into three regions: Northern Europe, Southern Europe and Northeast Asia. Transportation durations were calculated assuming the distances from these regions to Surabaya, Indonesia, and summarised in the Table 5. Surabaya was selected as being located halfway along the interconnector route with well-established port infrastructure and many sheltered areas.

Table 5 Ditstances from cable plants to Indonesia

Lead time

The manufacturing HVDC cable is a time-consuming process and involves a number of sequential operations from conductor stranding, insulation extrusion or lapping, intermediate lead/PE sheathing, armouring to yarn bedding of the external sheath. According to an assessment performed by Europacable [14], the combined production capacity of Europe-based HV submarine cable manufacturers (extruded or mass impregnated, HVDC or HVAC) is in the order of 5000 km per annum. Albeit plant capacity differs from one facility to another, for the purpose of this report, a delivery capacity of approximately 500 km per annum of HVDC 525 kV cable is considered representative. Given the required length for this interconnector (2 × 3200 km), the plant delivery limitation raises a serious challenge for the execution of this project. Based on this average plant capacity, the number of suppliers required to simultaneously manufacture sections of the HVDC cables was estimated and presented in Fig. 11; adopting various installation campaign durations ranging from 2 to 4 years. The proposed philosophy relies on delivering cable with multiple suppliers (and locations) at a pace that allows continuous supply to the CLV(s) during the entire installation campaign without, or with minimum, interruption.

Fig. 11
figure 11

Required delivery capacity (km/year/supplier) vs number of HVDC cable suppliers

According to this initial estimate, it is anticipated that 3–5 suppliers are required to manufacture cable sections simultaneously to meet the proposed delivery schedules. Furthermore, the production requirements presented are based upon the assumption that manufacturing facilities will be fully dedicated to this specific project, with no spare capacity to fabricate cables for other clients and no limitations caused by the manufacturers supply chain, over the 2- to 4-year project construction phase. This exclusivity constraint is unlikely to be acceptable to cable manufacturers and, therefore, lower delivery capacities are to be expected.

Cable transport and installation

Cable lay vessel market

CLVs are either owned by cable manufacturers such as Nexans, NKT and Prysmian offering EPCI solutions, or by installation contractors active across the entire offshore industry (oil and gas, offshore wind, power and communication undersea cables). These construction vessels include either one or two in-built cable carousels with individual capacities ranging from 5000 to 10,000 te. Capacity of typical CLVs currently (or about to be) available on the market are summarised in Fig. 12. Additional vessels are presently under construction to further strengthen the worldwide CLV fleet with a clear trend of increasing cable carousel capacity. For the purpose of this report, a generic CLV with 10,000 te cable capacity and 12-knot transit speed has been assumed to represent the market situation in 5–10 years’ time, the expected execution timeline for the commencement of works on this interconnector project (Fig. 13).

Fig. 12
figure 12

Carousel capacities of CLVs

Fig. 13
figure 13

Typical CLV—Isaac Newton (Source Jan de Nul)

In addition to the CLV fleet, offshore construction vessels (OCVs) dedicated to the oil and gas industry can be easily converted to include large capacity portable carousels installed on the deck, an example is the McDermott North Ocean 102 which is fitted with a 6000 te reel carousel. Further, construction vessels need to comply with stringent requirements to be allowed to operate in Australian waters and OCVs are more likely to be compliant and requires less upgrades compared to CLVs that have never worked in Australian waters.

Installation with CLV only (no transport vessel)

Most of the long subsea HVDC cable projects executed to date were located within 500–1000 km from the HVDC cable manufacturing facilities enabling the CLV to act as the transport and installation vessel, transiting back and forth from the offshore cable route to the plant for reloading each cable section.

The CLV typical transit durations from Indonesia (Surabaya) to Northern Europe, Southern Europe and Northeast Asia are 37 days, 26 days and 11 days, respectively (one way). Based on a CLV capacity of 10,000 te (equivalent to approximately 200 km of cable), a total of 31 reloads (32 loads) will be required to complete the entire interconnector offshore installation scope.

HVDC cable lay durations have been estimated accounting for the various activities involved including:

  • CLV transit back and forth between the manufacturing facility and the offshore cable route;

  • transpooling cable from the manufacturing facility quayside into the CLV carousel;

  • recovery of the cable end of precedent section and cable jointing;

  • normal lay the current cable section along the offshore route.

The following assumptions have been adopted to calculate the operation durations:

  • Carousel capacity of CLV, 10,000 te of cable (equivalent to 200 km)

  • Vessel carousel transpooling speed, 500 m/h

  • Average cable lay rate, 500 m/h

  • Joint duration including subsea recovery of preceding section, 7 days

  • Joint on deck (no subsea recovery), 6 days

  • Weather allowance (stand-by provision), 10% for transit and 20% for laying

On this basis, on average, 36 days are required to lay 200 km of HVDC cable once the vessel reaches Indonesian/Australian waters; laying operations includes retrieval of the cable end from the preceding cable lay section, jointing and laying the subsequent cable section (assuming cable delivered in 100 km sections).

If this approach were to be adopted for this project, depending on the number of simultaneous CLVs (assumed one to three CLVs in this study) and the various plant locations, the overall cable installation campaign would last between 2 years (three CLVs and Plants in Northeast Asia) to 11 years (one CLV and Plants in Northern Europe), continuously, as presented in Fig. 14.

Fig. 14
figure 14

Required duration to complete interconnector scope based on CLV only (no transport vessels) depending on plant location (years of continuous service)

CLVs require specialist personnel and equipment onboard, which is inherently reflected into vessel day rates; whereas transport vessels have a reduced crew onboard, that is, it is generally limited to marine crew. It is unlikely that cost-effectiveness can be achieved through a strategy implying extensive CLV transit time unless construction crew is periodically mobilised and demobilised according to construction and transit modes.

Installation with transport vessels and CLVs

An integrated approach combining CLVs and transport vessels has been studied. This strategy is based on the CLV(s) remaining along the cable route vicinity (between Australia and Singapore) during the entire installation campaign whilst transport vessels transit back and forth from manufacturing plants to CLV to ensure operational continuity and avoid excessive CLV stand-by durations (and associated costs).

Large basket or reel carousels are used both for cable storage at manufacturing plants and marine transportation. The carousel assembly includes a circular base grillage to interface with the Transport Vessel, a turntable and a drive system, a loading tower with a spooling tensioner for loading/unloading, a control cabin, chutes and deflectors to safely route the cable in and out the carousels. Characteristics of high capacity carousels are summarised in Table 6. It is assumed, and likely to be preferred, that equipment required for cable transpooling remains onboard transport vessels during the entire installation campaign (Fig. 15).

Table 6 Typical portable carousel characteristics
Fig. 15
figure 15

Portable carousel with loading equipment set-up (source Swan Hunter)

Depending on the adopted transportation strategy, this large quantity of HVDC cable can be shipped from the manufacturing plant(s) to Indonesia/Australia, using different types of heavy transport vessels available on the market.

Heavy lift vessels (HLV)

HLVs are one of the most common transportation vessels used for shipment of oversized equipment cross-continents travelling at a service speed up to 17 knots. These vessels are typically equipped with dual cranes of unit capacity ranging from 300 to 900 te and large cargo holds. Generally, HLVs offer a flush deck of approximately 80–100 m in length, 26–28 m in beam and a deadweight of 10,000–12,000 te. The vessel deadweight and stability requirement are expected to be the governing parameters defining the maximum amount of cable a HLV can carry per trip. Accounting for these limitations, it has been assumed that a HLV should be able to accommodate two off 5000 te carousels (23 m in diameter) and the associated cable spooling equipment, as illustrated in Fig. 16. HLV cranes will be used to mobilise the empty carousels and spooling equipment on deck.

Fig. 16
figure 16

HLV with 2 off 5000 te carousels on deck

Module carrier vessels (MCV)

The specificity of the MC-class (module carrier) vessels is the large vessel breadth (up to 34 m) offering a large clear deck suitable to transport large and bulky heavy cargo at a service speed of 13 knots. These vessels can accommodate up to three 7000 te carousels (28 m in diameter), illustrated in Fig. 17 either loaded out through skidding/rolling in and out from a marine base quayside or remain on vessel deck during the entire project duration.

Fig. 17
figure 17

Module carrier vessel with 3 off 7000 te carousels on deck

Cargo barges (CB)

Large cargo barges, typically 300–400 ft barges, offer similar deck area and deadweight to HLVs and MCVs. Cargo barges can either be towed to site, at relatively slow speed, or loaded onto semi-submersible heavy transport vessels and floated-off once they reach the destination and anchored in sheltered waters. The main advantage of this strategy is to avoid extended demurrage time of heavy transport vessels waiting for the CLVs to complete cable section installation, increasing the overall schedule flexibility level. The typical characteristics of 400 ft cargo barges are 122 m in length, 36 m in width and 20,000 te deadweight for a lightship of 4000 te. Two off 5000 te carousels in addition to the spooling equipment have been assumed per cargo barge, see Fig. 18. Higher payloads may be accommodated by 400 ft barges but, to cover a wider range of cargo barges (300–400 ft barges) and for the purpose of this assessment, this loading plan has been conservatively adopted (seagoing stability will need to be confirmed).

Fig. 18
figure 18

400 ft cargo barge with 2 off 5000 te carousels on deck

Semi-submersible heavy transport vessels (SHTV)

SHTVs offer versatile loading methods by means of float-on/off, skid-on/off, roll-on/off and lift-on/off operations. SHTVs include deck space ranging from 130 to 160 m in length and 40–50 m in breadth; transiting at a service speed of 13 knots. This transportation option has been investigated assuming the cargo barges and loading plan previously described, i.e. 400 ft barges with two off 5000 te carousels (and spooling equipment). The SHTVs proceed with the float-on/off operations of the pre-loaded cargo barges at cable manufacturing plants and at destination, an illustration of this transportation method is provided in Fig. 19.

Fig. 19
figure 19

Semi-submersible heavy transport vessel with a 400 ft cargo barge

The following transportation strategies were identified and are summarised in Table 7.

  • Scenario 1: HLV—2 × 5000 te carousels permanently installed on deck for the project duration.

  • Scenario 2: MCV—3 × 7000 te carousels permanently installed on deck or skid-in/off, roll in/off from a quayside.

  • Scenario 3: Cargo barges being towed—2 × 5000 te permanently installed.

  • Scenario 4: Semi-sub vessels—barge float in/off with 2 × 5000 te carousels permanently installed on the barge.

Table 7 Transportation vessels–typical characteristics

Several transportation strategies were investigated to screen out the various logistical options and identify the most efficient approaches from a project duration standpoint. It was assumed that either one or two CLVs were continuously chartered for this installation campaign; CLVs being either laying cable, transiting to meet the transport vessels or loading up cable sections; avoiding any personnel demobilisation (other than crew swap-out) during the entire installation campaign.

It was assumed that cable section transpooling operations between the CLV and the transport vessels will be performed at the nearest sheltered waters from the CLV as the cable installation progresses along the interconnector route. To estimate the installation campaign durations, 2-day transit time was considered for the CLV to meet the transport vessels in demurrage.

Adopting this strategy, cable lay of 200 km requires 57 days (including CLV transit to transport vessels, cable transpooling operations and offshore construction operations), which leads to a total duration of approximately 5 years and 2.5 years for 1 CLV and 2 CLVs, respectively.

The number of transport vessels to continuously feed the CLVs with cable sections to avoid any downtime are presented in Fig. 20 for the various transport vessel types and two installation campaign durations (2.5 and 5 years).

Fig. 20
figure 20

Required number of transport vessels (1 or 2 CLVs)

By way of example, assuming the project decides to complete the cable laying operations within 2.5 years, cable plants are located in Northern Europe, and HLV is selected as the transport vessel type, this strategy would require six HLVs (all fitted with 2 × 5000 te carousels) to rotate back and forth from plants to Indonesian/Australian sheltered waters during the entire 2.5-year operation.

Cost estimate

The capital expenditure covering the subsea HVDC cable supply, transportation and installation phases has been estimated based on the cable technical definition developed previously, “HVDC cable cross-section design” and “Route selection”.

For the purpose of this assessment, the adopted transportation and installation strategy is based on a 2.5-year installation campaign carried out by two CLVs and supported by four HLVs to continuously transport cable sections manufactured in Northern Europe.

A subsea cable benchmark was performed across the main subsea HVDC projects executed over the last decade. The actual supply cost of an HVDC cable depends on many design aspects including conductor material (copper versus aluminium), service water depth (impacting armouring design), water blocking capability and type of insulation. Consequently, it is anticipated that cable cost per unit length will vary along the interconnector route, however, it was concluded from this benchmark that an average cable cost of 0.6 $/kW/km is a reasonable figure for this high-level assessment. The main input data considered for this cost estimate are presented in Table 8.

Table 8 Cost estimates assumptions (USD)

The breakdown of the subsea cable cost estimates is summarised in Table 9 and Fig. 21.

Table 9 Subsea cable cost estimates (in million USD)
Fig. 21
figure 21

Subsea cable cost distribution

The overall subsea cable project cost has been estimated to be approximately $6 billion.

This interconnector cost estimate highlights that the project cost is mainly driven by the HVDC cable supply cost. Although the transportation of approximately 320,000 te of cable raises significant supply and logistic challenges, the actual transportation cost remains low in comparison to the overall project cost. Nevertheless, a robust transportation strategy is considered highly desirable to minimise project schedule risk and knock-on effects on the cable lay activities for which expensive spreads will be mobilised and notwithstanding the potential risk to the product from excessive storage and for installed sections remaining on the seabed for a long duration before system testing and commissioning.

Phased construction development

In light of the identified HVDC cable manufacturing and logistic challenges of such a long interconnector (2 × 3200 km), a phased development approach has the potential to offer significant benefits and enhance overall project feasibility. This megaproject can be divided into more manageable successive packages by connecting the Indonesian grid first, and subsequently Singapore; resulting in a 4-phase project (based ultimately on a bipolar interconnector).

Two variations of this staged development exist, presented in Table 10, depending on whether the priority, during the second phase, is to have an Australia–Indonesia bipolar interconnector (full capacity) or an Australian–Singapore monopolar interconnector (half capacity).

Table 10 Phased development approach—Australian–Indonesia–Singapore

Option 1 consists of installing, first, the two parallel sections of subsea cables between Australia and Indonesia, enabling the interconnector capacity to reach its full design capacity (2.4 GW) earlier compared to Option 2, generating potentially higher revenue (depending on relative country feed-in tariff) during the intermediate phases.

The cable track length from Australia to Indonesia, Bali was arbitrary selected as the intermediate substation location for this study, is approximately 1400 km (as opposed to 3200 km to Singapore). The subsequent section from Indonesia to Singapore is about 1800 km long.

An initial Australia–Indonesia monopole interconnector can be laid by a single CLV within a year (with transport vessels) and supplied from two to three simultaneous cable manufacturers.

This phased development strategy can potentially offer the following advantages:

  • lower initial investment and risk profile;

  • reduced cost of capital and improved project cash flow position;

  • generating revenue from the installed cable sections for the subsequent construction phases;

  • ability to integrate lessons learnt from previous phases;

  • benefit from HVDC technology development for the final phases;

  • increased market tension of HVDC cable manufacturers and installation contractors;

  • ability to adapt from geopolitical and legislation changes during the course of the project.

Conclusions and discussions

Connecting Australia to Singapore through an HVDC subsea interconnector, although relatively ambitious, is technically feasible. A potentially suitable marine route has been identified, 3200 km in length, which departs from north of Western Australia, crosses the Timor Trough (up to 1900 m water depth), crosses Indonesia (east of Bali) and runs through the Java Sea to Singapore. Adopting the current technology this interconnector can be configured in a bipolar mode to offer 2.4 GW power capacity, using two individual and identical 525 kV HVDC underwater cables, with most likely different designs along the route, such as copper and aluminium conductors for the shallow and deepwater sections respectively, and a mass-impregnated or XLPE insulation.

The closest analogues, to date, of the anticipated interconnector key characteristics are summarised in the Table 11.

Table 11 Project analogues

This Australia—Singapore power link has the potential to offer valuable benefits, not only to both countries, but also to Southeast Asia collectively in the long term. It will enhance Singapore energy security and decrease its exclusive reliance on natural gas for power generation whilst contributing to reduce its carbon footprint. Rooftop solar is the only, and limited, renewable energy source available to Singapore and a long interconnector is one of the few credible options to lower the country’s emission level. Besides, the Australian renewable industry will benefit from this megaproject by significantly strengthen its workforce skillset in the renewable sector which can be leveraged for subsequent large-scale renewable developments in northwest Australia including solar, wind and green hydrogen projects.

However, this study identified the following key challenges that need to be overcome:

  • HVDC cable supply: HVDC cable lead time and current worldwide plant production capacity is currently a major hindrance to the feasibility of this project. The required cable quantity (2 × 3200 km) exceeds the average annual plant capacity worldwide. Besides, this project will most likely be in competition with other HV projects (HVAC and HVDC) to secure manufacturing slots. An in-depth appreciation of the HVDC cable market and individual cable manufacturing capability, respective strengths and weaknesses shall be undertaken in detail as well as planned/possible plant capacity expansion to define a robust procurement strategy, most likely involving multiple simultaneous manufacturers.

  • HVDC cable transport and installation: This interconnector length combined with the remote installation location from manufacturing facilities create unique cable transportation challenges that can be technically addressed by chartering a fleet composed of heavy transport vessels ranging from HLVs, MCVs, semi-submersible vessels and/or cargo barges. The installation/transportation fleet selection will depend on the number and locations of cable manufacturers, the level of desired schedule float between transportation fleet and installation fleet and associated risk profile whilst minimising capital expenditure. The interconnector construction phase requires two cable lay vessels mobilised for a 2.5-year duration with a heavy transport vessel fleet continuously transiting between manufacturing facilities and Indonesian/Australian sheltered waters to feed the CLVs with cable sections.

  • Route through Timor Trough: The marine route crosses the Timor Trough reaching 1900 m water depth with high seabed gradients. Specific attention will be required to the cable cross-section design to account for high lay tension during installation and hydrostatic pressure in service (up to 200 bar at this depth). The survey operations and route selection process are anticipated to require extensive engineering to address the challenges pose by possible mass flow slides from the region seismic activity, high seabed slopes and wide cable corridors required to enable future repair (Omega loop). High specification CLVs will be needed to enable safe cable deployment in this deep section.

  • Indonesian territorial waters: Obviously, Indonesia will be a major stakeholder for this development, having most of the interconnector length crossing Indonesian territorial waters. Early engagement with authorities will be paramount to successfully and timely secure approval of the Permit in Principle enabling cable installation within the country jurisdiction.

  • Seabed congestion between Indonesia and Singapore: The route section from Indonesia to Singapore is exceptionally shallow and flat with a high level of seabed congestion. Many crossings with existing pipelines and communication cables are expected with a need to protect the link against damage from fishing activities, ship dragged anchors and dropped objects, most likely requiring the cables to be trenched over 60% of the cable route.

The capital expenditure of this subsea interconnector project is anticipated to reach $6 billion and is mainly driven by the HVDC cable supply cost; the cable transportation represents only a small fraction of the overall project budget. However, the schedule risk profile of the complex project logistic is relatively high as it can impact the cable laying operations for which expensive spreads will be mobilised.

From project planning and financing perspectives, a staged development approach with an initial monopolar link between Australia and Indonesia appears attractive in light of the scale of the project and installation campaign duration. The tri-party power link model is currently being implemented by the EuroAsia interconnector project between Israel, Cyprus and Greece, which is, at the time of writing, the closest HVDC project analogue. The benefits for Indonesia include a carbon content reduction of its electricity and a response to the expected high demand growth in the coming decades. Also, Indonesia has the world’s second largest geothermal energy resource (after Iceland) and it is expected that its share of clean electricity from geothermal generation will grow significantly in the future.