Skip to main content
Log in

A Fixed Start Scheduling Approach for Repetitive Construction Projects

  • Construction Management
  • Published:
KSCE Journal of Civil Engineering Aims and scope Submit manuscript

Abstract

In the face of the high variability in the completion of construction projects, the following research is generated. In the literature we can find several proposals to program projects, however, the variability of the activities causes high variability in the completion date of the projects. We hope that the proposed method, by controlling the start of activities, will ensure the completion date of the projects, by fixing the start of every activity with a high level of probabilistic confidence for the planned project duration. The proposed fixed start method (FSM) was tested in two case studies by using discrete event simulation. Project completion duration results were compared with the critical path method (CPM) and the program evaluation and review technique (PERT). Project completion was evaluated in the case studies by the coefficient of variance (COV), mean, and variance. The new method decreased the scheduled duration variability while meeting project completion times.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Institutional subscriptions

Similar content being viewed by others

Abbreviations

ATAED e :

Accumulative total advance for estimated duration

ATED e :

Accumulated total estimated ending days

ATSD p :

Accumulated total planned start days

\({\rm{atsd}}_{t,i}^p\) :

Accumulated total planned start days per unit (i) in function of time (t)

\({\rm{atsd}}_{t,i}^e\) :

Accumulated total estimated start days per unit (i) in function of time (t)

bf i :

Time Buffer for each activity (j)

d :

Duration of activity

\(d_j^e\) :

Estimated duration for each activity (j)

\(d_j^p\) :

Planned duration for each activity

(j)edt,i :

Indicator of ends per unit (i) and activity (j) in function of time (t)

F e :

Estimated finish of units and activities

\(f_{i,j}^e\) :

Estimated finish of unit (i) and activity (j)

F p :

Planned finish of units and activities

\(f_{i,j}^p\) :

Planned finish of unit (i) and activity (j)

i :

Units

j :

Activities

L i :

Lapse of days between the beginning of units for the same activities

M :

Number of activities

N :

Number of repetitive units

np j :

Number of personal per activity (j), crew elements

P :

Production of a working crew

Q :

Amount of work in units per activity

R a :

Adjusted production rate

R p :

Production rate

S :

Start of units and activities

S i,j :

Start of unit (i) and activity (j)

SD p j :

Adjusted production rate planned per activity

sd t,i :

Adjusted production rate, of unit (i) in function of time (t)

t :

Time

T 1 :

Total time of the first repetitive unit

T p :

Desired total time of the project

TP e :

Estimate total time of the project

TAED e :

Total advance for estimated duration (days)

TPD t :

Total personnel or labor per day

TSD e :

Total estimated starting day

\(tsd_{i,j}^e\) :

Total estimated starting day, per unit (j) in function of time (t)

TSD p :

Total planned starting day

α & β:

Shape parameter (Beta Distribution)

References

  • AbouRizk SM, Halpin DW, Wilson JR (1994) Fitting beta distibutions based on sample data. Journal of Construction Engineering and Management 120(2):288–305, DOI: 10.1061/(ASCE)0733-9364(1994) 120:2(288)

    Google Scholar 

  • Ammar MA (2013) LOB and CPM integrated method for scheduling repetitive projects. Journal of Construction Engineering and Management 139(1):44–50, DOI: 10.1061/(ASCE)CO1943-7862.0000569

    Google Scholar 

  • Arditi D, Albulak MZ (1986) Line-of-balance scheduling in pavement construction. Journal of Construction Engineering and Management 112(3):411–424,DOI: 10.1061/(ASCE)0733-9364(1986)112:3(411)

    Google Scholar 

  • Arditi D, Tokdemirl OB, Suh K (2002) Challenges in line-of-balance scheduling. Journal of Construction Engineering and Management 128(6):545–556, DOI: 10.1061/(ASCE)0733-9364(2002)128:6(545)

    Google Scholar 

  • Assafl SA, Al-Hejji S (2006) Causes of delay in large construction projects. International Journal of Project Management 24(4):349–357, DOI: 10.1016/j.ijproman.2005.11.010

    Google Scholar 

  • Bonett DG (2006) Confidence interval for a coefficient of quartile variation. Computational Statistics & Data Analysis 50(11):2953–2957, DOI: 10.1016/j.csda.2005.05.007

    MathSciNet  MATH  Google Scholar 

  • Byrne MD (2013) How many times should a stochastic model be run? An approach based on confidence intervals. In: Proceedings of the 12th international conference on cognitive modeling, Carleton University, Ottawa, Canada, 445–450

    Google Scholar 

  • Chapman RJ (2012) Simple tools and techniques for enterprise risk management. John Wiley and Sons, New York, NY, USA, DOI: 10.1002/9781118467206

    Google Scholar 

  • Chrzanowskil EN, Johnston DW (1986) Application of linear scheduling. Journal of Construction Engineering and Management 112(4):476–491, DOI: 10.1061/(ASCE)0733-9364(1986)112:4(476)

    Google Scholar 

  • Chual DK, Shen LJ (2005) Key constraints analysis with integrated. Journal of Construction Engineering and Management 131(7):753–764, DOI: 10.1061/(ASCE)0733-9364(2005)131:7(753)

    Google Scholar 

  • Ciccarellil JJ, Cohen MW (2005) Window analysis: The method and the myth. AACEInternational Transactions 2005:05.1

  • Clark CE (1962) The PERT model for the distribution of an activity time. Operations Research 10(3):405–406, DOI: 10.1287/opre.10.3.405

    Google Scholar 

  • Damci A, Arditi D, Polat G (2016) Impacts of different objective functions on resource leveling in line-of-balance scheduling. KSCE Journal of Civil Engineering 20(1):58–67, DOI: 10.1007/sl2205-015-0578-7

    Google Scholar 

  • De La Garzal JM, Prateapusanond A, Ambani N (2007) Preallocation of total float in the application of a critical path method based construction contract. Journal of Construction Engineering and Management 133(11):836–845, DOI: 10.1061/(ASCE)0733-9364(2007)133:11(836)

    Google Scholar 

  • El-Rayes K (2001) Object-oriented model for repetitive construction scheduling. Journal of Construction Engineering and Management 127(3): 199–205, DOI: 10.1061/(ASCE)0733-9364(2001)127:3(199)

    Google Scholar 

  • Faridil AS, El-Sayegh SM (2006) Significant factors causing delay in the UAE construction industry. Construction Management and Economics 24(11):1167–1176, DOI: 10.1080/01446190600827033

    Google Scholar 

  • Fente J, Schexnayder C, Knutson K (2000) Defining a probability distribution function for construction simulation. Journal of Construction Engineering and Management 126(3):234–241, DOI: 10.1061/(ASCE) 0733-9364(2000)126:3(234)

    Google Scholar 

  • Gantt HL (1913) Work, wages and profits. The Engineering Magazine Co., New York, NY, USA, DOI: 10.1086/251864

    Google Scholar 

  • Goldratt EM (1990) What is this thing called the Theory of Constraints and how should it be implemented? North River Press, Great Barrington, MA, USA

    Google Scholar 

  • Hajdu M, Bokor O (2016) Sensitivity analysis in PERT networks: Does activity duration distribution matter? Automation in Construction 65:1–8, DOI: 10.1016/j.autcon.2016.01.003

    Google Scholar 

  • Halpin DW (1973) An investigation of the use of simulation network for modeling construction operations. PhD Thesis, University of Illinois, Champaign, IL, USA

    Google Scholar 

  • Harrisl RB, Ioannou PG (1998) Scheduling projects with repeating activities. Journal of Construction Engineering and Managment 124(4):269–278, DOI: 10.1061/(ASCE)0733-9364(1998)124:4(269)

    Google Scholar 

  • Heidelberger P, Welch PD (1983) Simulation run length control in the presence of an initial transient. Operations Research 31(6):1109–1144, DOI: 10.1287/opre.31.6.1109

    MATH  Google Scholar 

  • Hoppl WJ, Spearman ML (2008) Factory physics, 3rd edition. Waveland Press, Long Grove, IL, USA

    Google Scholar 

  • Huang R-Y, Sun K-S (2006) Non-unit-based planning and scheduling of repetitive construction projects. Journal of Construction Engineering and Management 132(6):585–597, DOI: 10.1061/(ASCE)0733-9364(2006)132:6(585)

    Google Scholar 

  • Izmailov A, Korneva D, Kozhemiakin A (2016) Project management using the buffers of time and resources. Procedia -Social and Behavioral Sciences 235:189–197, DOI: 10.1016/j.sbspro.2016.11.014

    Google Scholar 

  • Kang L, Parkl IC, Lee B (2001) Optimal schedule planning for multiple, repetitive construction process. Journal of Construction Engineering and Management 127(5):382–390, DOI: 10.1061/(ASCE)0733-9364 (2001)127:5(382)

    Google Scholar 

  • Keller JE (1960) Critical-path planning and scheduling: Mathematical basis. Operations Research 9(3):296–435, DOI: 10.1287/opre.9.3.296

    MathSciNet  Google Scholar 

  • Khamooshi H, Cioffi DF (2013) Uncertainty in task duration and cost estimates: Fusion of probabilistic forecasts and deterministic scheduling. Journal of Construction Engineering and Managment 139(5):488–497, DOI: 10.1061/(ASCE)CO.1943-7862.0000616

    Google Scholar 

  • Koskela L (2000) An explotration toward a production theory and its application to construction. VTT Technical Research Centre of Finland, Helsinki, Finland

    Google Scholar 

  • Lee D-E, Bae T-H, Arditi D (2012) Advanced stochastic schedule simulation system. Civil Engineering and Environmental Systems 29(1):23–40, DOI: 10.1080/10286608.2011.637623

    Google Scholar 

  • Lee H-S, Ryu H-Q, Yu J-H, Kim J-J (2005) Method for calculating schedule delay considering lost productivity. Journal of Construction Engineering and Management 131(11):1147–1154, DOI: 10.1061/(ASCE)0733-9364(2005)131:11(1147)

    Google Scholar 

  • Lorterapong P, Ussavadilokrit M (2013) Construction scheduling using the constraint satisfaction problem method. Journal of Construction Engineering and Management 139(4):414–422, DOI: 10.1061/(ASCE)CO 1943-7862.0000582

    Google Scholar 

  • Lucko G (2008) Productivity scheduling method compared to linear and repetitive project scheduling methods. Journal of Construction Engineering and Managment 134(9):711–720, DOI: 10.1061/(ASCE)0733-9364(2008)134:9(711)

    Google Scholar 

  • Lucko G (2009) Productivity scheduling method: Linear schedule analysis with singularity functions. Journal of Construction Engineering and Management 135(4):246–253, DOI: 10.1061/(ASCE)0733-9364 (2009)135:4(246)

    Google Scholar 

  • Malcolm DQ Rosebooml JH, Clarkl CE, Fazar W (1959) Application of a technique for a research and development program evaluation. Operations Research 7(5):646–669, DOI: 10.1287/opre.7.5.646

    Google Scholar 

  • Martinez JC (1996) STROBOSCOPE: State and resource based simulation of construction processes. PhD Thesis, University of Michigan, Ann Arbor, M, USA

    Google Scholar 

  • Martinezl JC, Ioannou PG (1999) General-purpose systems for effective construction simulation. Journal of Construction Engineering and Management 125(4):265–276, DOI: 10.1061/(ASCE)0733-9364(1999) 125:4(265)

    Google Scholar 

  • Mouri H (2013) Log-normal distribution from a process that is not multiplicative but is additive. Physical Review E 88(4):042124, DOI: 10.1103/PhysRevE.88.042124

    Google Scholar 

  • Nguyenl QT, Chua DH (2014) Criticality of schedule constraints -Classification and identification for project management. Journal of Engineering, Project, and Production Management 4(1):17–25, DOI: 10.32738/JEPPM.201401.0003

    Google Scholar 

  • Nguyenl TQ, Chua DK (2015) Preemptive constraint analysis in construction schedules. Journal of Computing in Civil Engineering 29(5):04014062, DOI:10.1061/(ASCE)CP.1943-5487.0000363

    Google Scholar 

  • Nguyenl LD, Phanl DH, Tang LC (2013) Simulating construction duration for multistory buildings with controlling activities. Journal of Construction Engineering and Management 139(8):951–959, DOI: 10.1061/(ASCE)CO.1943-7862.0000677

    Google Scholar 

  • Ockl JH, Han SH (2010) Measuring risk-associated activity’s duration: A fuzzy set theory application. KSCE Journal of Civil Engineering 14(5):663–671, DOI: 10.1007/sl2205-010-1003-x

    Google Scholar 

  • Poshdar M, Gonzalezl VA, Raftery M, Orozco F (2014) Characterization of process variability in construction. Journal of Construction Engineer Managment 140(11):1–9, DOI: 10.1061/(ASCE)CO.1943-7862.0000901

    Google Scholar 

  • Russelll MM, Howell Q Hsiangl SM, Liu M (2013) Application of time buffers to construction project task durations. Journal of Construction Engineering and Management 139(10):1–10, DOI: 10.1061/(ASCE) CO. 1943-7862.0000735

    Google Scholar 

  • Russelll MM, Hsiangl SM, Liu M, Wambeke B (2014) Causes of time buffer and duration variation in construction project tasks: Comparison of perception to reality. Journal of Construction Engineering and Management 140(6):4014016, DOI: 10.106 l/(ASCE)CO 1943-7862. 0000819

    Google Scholar 

  • Sackey S, Kim BS (2019) Schedule risk analysis using a proposed modified variance and mean of the original program evaluation and review technique model. KSCE Journal of Civil Engineering 23(4):1484–1492, DOI: 10.1007/s12205-019-1826-z

    Google Scholar 

  • Sadeghi N, Fayekl AR, Ingolfsson A (2012) Simulation-based approach for estimating project completion time of stochastic resource-constrained project networks. Journal of Computing in Civil Engineering 26(4):558–560, DOI: 10.1061/(ASCE)CP1943-5487.0000165

    Google Scholar 

  • Schexnayder C, Knutson K, Fente J (2005) Describing a beta probability distribution function for construction simulation. Journal of Construction Engineering and Management 131(2):221–229, DOI: 10.1061/(ASCE) 0733-9364(2005)131:2(221)

    Google Scholar 

  • Steyn H (2001) An investigation into the fundamentals of critical chain project scheduling. International Journal of Project Managemen 19(6):363–369, DOI: 10.1016/S0263-7863(00)00026-0

    Google Scholar 

  • Su Y, Lucko G (2016) Linear scheduling with multiple crews based on line-of-balance and productivity scheduling method with singularity functions. Automation in Construction 70:38–50, DOI: 10.1016/j.autcon.2016.05.011

    Google Scholar 

  • Taghaddos H, Hermann U, AbouRizk S, Mohamed Y (2014) Simulation-based multiagent approach for scheduling modular construction. Journal of Computing in Civil Engineering 2%(T) 21-21A, DOI: 10.1061/(ASCE)CP.1943-5487.0000262

    Google Scholar 

  • Tang Y, Liu R, Sun Q (2014) Schedule control model for linear projects based on linear scheduling method and constraint programming. Automation in Construction 37:22–37, DOI: 10.1016/j.autcon.2013. 09.008

    Google Scholar 

  • Tang Y, Liu R, Wang F, Sun Q, Kandil AA (2018) Scheduling optimization of linear schedule with constraint programming. Computer-Aided Civil and Infrastructure Engineering 33(2):124–151, DOI: 10.1111/ mice. 12277

    Google Scholar 

  • Thabet W, Beliveau Y (1994) HVLS: Horizontal and vertical logic scheduling for multistory projects. Journal of Construction Engineering and Management 120(4):875–892, DOI: 10.1061/(ASCE)0733-9364 (1994)120:4(875)

    Google Scholar 

  • Thomas HR Hormanl MJ, de Souzal UE, Zavfski I (2002) Reducing variability to improve performance as a lean construction principle. Journal of Construction Engineering and Management 128(2): 144–154, DOI: 10.1061/(ASCE)0733-9364(2002)128:2(144)

    Google Scholar 

  • Wambekel WB, Hsiangl SM, Liu M (2011) Causes of variation in construction task starting times and duration. Journal of Construction Engineering And Management 137(9):663–677, DOI: 10.1061/ (ASCE)CO1943-7862.0000342

    Google Scholar 

  • Whiteman W, Irwig H (1998) Disturbance scheduling technique for managing renovation work. Journal of Construction Engineering and Management 114(2):191–213, DOI: 10.1061/(ASCE)0733-9364(1988)114:2(191)

    Google Scholar 

  • Yang J-B, Wei P-R (2010) Causes of delay in the planning and design phases for construction projects. Journal of Architectural Engineering 16(2):80–83, DOI: 10.1061/(ASCE)1076-0431(2010)16:2(80)

    Google Scholar 

  • Zolfaghar HR, Afshar A, Abbasnia R (2014) CPMLOB scheduling method for project deadline constraint satisfaction. Automation in Construction 48:107–118, DOI: 10.1016/j.autcon.2014.09.003

    Google Scholar 

  • Zou X, Fangl SC, Huangl YS, Zhang LH (2016) Mixed-integer linear programming approach for scheduling repetitive projects with time-cost trade-off consideration. Journal of Computing in Civil Engineering 31(3):1–6, DOI: 10.1061/(ASCE)CP1943-5487.0000641

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Francisco Orozco.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Moreno, F., Orozco, F., Rojas, O. et al. A Fixed Start Scheduling Approach for Repetitive Construction Projects. KSCE J Civ Eng 24, 1671–1682 (2020). https://doi.org/10.1007/s12205-020-1429-8

Download citation

  • Received:

  • Revised:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s12205-020-1429-8

Navigation